MahaRERA · the public record
SUNSHINE INFINITY
WADALA WEST · SQ INFRASTRUCTURE PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2019
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51900003947
Delivery and registration
When is the project declared for completion?
SUNSHINE INFINITY is registered with MahaRERA as P51900003947 and the promoter has declared completion for 31 Dec 2019.
31 Dec 2019
declared completion
81months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51900003947 |
| Registered on | 07 Aug 2017 |
| Promoter-declared completion | 31 Dec 2019 |
| Current status | Certificate Signed |
| Against today | about 81 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUNSHINE INFINITY record 10 quarterly progress reports since registration.
10quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
- Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for SUNSHINE INFINITY in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+36.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| SUNSHINE INFINITY | 1 | G+36 | - |
Legal and disputes
What disputes are disclosed?
4 complaints are on the MahaRERA record for SUNSHINE INFINITY, with orders passed in 4 of them.
4complaints
4with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000001070 | 04/10/2017 | V M GAWAND vs M/S. GRACE ERECTORS OF COMPANIES,BUILDER & DEVELOPERS | order passed |
| CC006000000079243 | 10/05/2019 | 1) Amar Shamji Veera & 2) Jinal Amar Veera vs 1) Sunshine Housing & Infrastructure Pvt Ltd & 2) SQ Infrastructure Pvt Ltd | order passed |
| CC006000000057931 | 05/02/2019 | Fanny Mehta & Ashit Mehta vs Sunshine Housing & Infrastructure Private Limited | order passed |
| CC006000000057934 | 05/02/2019 | Fanny Mehta & Ashit Mehta vs Sunshine Housing and Infrastructure Private Limited | order passed |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2019 | Subject : Revision of Proposed Date of Completion from 31st December 2018 to 30th June 2019. As per condition No. 53 of Letter of Intent Dated 26/04/2016 the eligibility o |
Location, Land & Connectivity
Located at WADALA WEST, SUMANTAI MAHATRE ROAD, Ward FNorth, Mumbai City, 400031. Per the filed land record, the plot is bounded to the north by 15 25 MTR WIDE SEWREE WADALA ESTATE SCHEME ROAD, to the south by 15 25 MTR WIDE SEWREE WADALA ESTATE SCHEME ROAD, to the east by PLOT NO 285 AND 295 and to the west by REHAB PLOT BEARING NO 286 TO 294 AND 294 A PART. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~104 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 104 km |
| Baner–Balewadi belt | 109 km |
| Pune Junction / city centre | 120 km |
| Pune Int'l Airport (Lohegaon) | 122 km |
| Kharadi / EON IT Park | 125 km |
| Magarpatta / Hadapsar IT | 126 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.