Mumbai/Project record

MahaRERA · the public record

Suraj Apartments

Santacruz West · Mala Co-Operative Housing Society Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 02 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900053591

Delivery and registration

When is the project declared for completion?

Suraj Apartments is registered with MahaRERA as P51900053591 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationP51900053591
Registered on10 Nov 2023
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Suraj Apartments record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Mala Co-Operative Housing is the promoter of record on 118 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

118projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Suraj Apartments in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 02 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Suraj Apartments1G+1131 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Santacruz West, Saraswati road, Mumbai City, Mumbai City, 400054. Per the filed land record, the plot is bounded to the north by Saraswati Road, to the south by CTS No G311 Jhaveri House, to the east by CTS No 312 Jolly Apartments and to the west by CTS NO G319A G318B and G317 81 Crest. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai City

Suraj Aureva
possession by Dec 2031 · Suraj Estate Developers LTD
Suraj Eterna
possession by Dec 2026 · Suraj Estate Developers LTD
Suraj Lumina
possession by Dec 2028 · Uditi Premises Pvt.ltd.
Suraj One Business Bay
possession by Dec 2031 · Iconic Property Developers PVT LTD
Suraj Park View 1
possession by Dec 2031 · Suraj Estate Developers LTD
Suraj Park View 2
possession by Dec 2026 · Suraj Estate Developers LTD

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026