MahaRERA Property Intelligence · Mumbai Suburban

SWANAND BLDG NO 33

P51800004914 · Nehru Nagar · promoter Hiranimanthan Builders And

Certificate SignedDue 30 Nov 2024

Delivery & Registration

MahaRERA registrationP51800004914
Registered on09 Aug 2017
Promoter-declared completion30 Nov 2024
Current statusCertificate Signed
Against todayabout 20 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Hiranimanthan Builders And is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
SWANAND CHS, BLDG NO 331G+2031 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Nov 202401 Jun 2023We are about to complete the entire development work of the project up to 16 floors as per the approved plans and shortly starting to give ‘Fit Out Possessions’ to the allottees.
30 Nov 202430 Dec 2020Awaiting further approvals, hence this time is required to Construct the further awaited full potential FSI.
30 Nov 202430 Nov 2024We had completed construction of project in full. Society also formed. No development work is pending. We had applied for Occupancy Certificate however it is delayed due to procedu

Location, Land & Connectivity

Located at Nehru Nagar, Nehru Nagar, Kurla, Mumbai Suburban, 400024. Per the filed land record, the plot is bounded to the north by BLDG NO 34, to the south by BLDG NO 32, to the east by ROAD and to the west by BLDG NO 31. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hiranimanthan Builders AND Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Hiranimanthan Builders AND Developers

Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban
Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban
Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban
Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban
Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Nehru Nagar

OM Nandadeep CO-OP. Hsg. Soc. LTD
possession by Oct 2026 · OM Nandadeep CO-OP Housing Society Limit
Ratnadeep Heights
possession by Oct 2026 · KRV Realty
Raghav Parijat
possession by Dec 2026 · Raghav Realty Developers
Hareshwar Pride
possession by Dec 2026 · Satyadeep Realtors Pvt. Ltd.
Nehru Nagar Vishwadham CHS LTD
possession by Dec 2026 · Apcon Construction Company
Nehru Nagar Nirmal C.h.s. Ltd
possession by Dec 2026 · Deraiya Realtors Private Limited

Major developers building in Nehru Nagar

Other RERA-registered projects in Mumbai Suburban

Swanand CO-Operative Housing Society Limited
possession by Dec 2027 · Samarpan Homes & Developers
Swapna Siddhi Chsl
declared completion Jun 2025 · Neev Construction
Swapna Sudha CHS LTD
possession by Dec 2026 · M/S AMO Group
Swapnapoorti
declared completion Dec 2021 · M/S Shiv Samruddhi Developers
Swaraj Kalash
declared completion Oct 2020 · RAJ Homes Pyramid Group
Swaroop Aditya Avenue
declared completion Jun 2025 · Swaroop Aditya Developer

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026