KANNAMWAR NAGAR SHANTIDHAM CHSL

KANNAMWAR NAGAR VIKHROLI EAST · HIRANIMANTHAN BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800025091

Delivery and registration

When is the project declared for completion?

KANNAMWAR NAGAR SHANTIDHAM CHSL is registered with MahaRERA as P51800025091 and the promoter has declared completion for 30 Mar 2026.

30 Mar 2026

declared completion

6months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800025091
Registered on18 Mar 2020
Promoter-declared completion30 Mar 2026
Current statusCertificate Signed
Against todayabout 6 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KANNAMWAR NAGAR SHANTIDHAM CHSL record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Hiranimanthan Builders is the promoter of record on 6 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KANNAMWAR NAGAR SHANTIDHAM CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
KANNAMWAR NAGAR SHANTIDHAM CSHL1G+2331 Mar 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KANNAMWAR NAGAR VIKHROLI EAST, KANNAMWAR NAGAR, Kurla, Mumbai Suburban, 400083. Per the filed land record, the plot is bounded to the north by ROAD AND BUILDING NO 92 AND 93, to the south by WIDE ROAD AND BUILDING NO 87 AND 88, to the east by BUILDING NO 190 and to the west by STATUE OF CHATRAPATI SHIVAJI MAHARAJ. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hiranimanthan Builders AND Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Hiranimanthan Builders AND Developers

Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban
Hiranimanthan Builders AND Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Vikhroli East

Shree Balaji 7
possession by Sep 2026 · Saptrishi Landmarks LLP
Unique Enclave Residency
possession by Sep 2026 · Fazal Shaikh
Vrindavan Elite
possession by Oct 2026 · Matrix Constructions
Meadows 83
possession by Oct 2026 · Shreeji Realtors
Eastern Groves Phase 2
possession by Dec 2026 · VL Savli Developers LLP
GS Casa
possession by Dec 2026 · Prach Realcon LLP

Major developers building in Vikhroli East

Other RERA-registered projects in Mumbai Suburban

Kapadia Avenue
declared completion Mar 2022 · L J Enterprise
Kapil Kunj
declared completion Dec 2018 · Niraj Mansukhlal VED
Karmayog
possession by Mar 2027 · Westin Developers Pvt. LTD
Karmyog
declared completion Dec 2022 · Krishnir Realtors AND Developers
Karwari CO-OP HSG Society Redevelopment Crystal Tower
declared completion Dec 2021 · MK Construction
Kasturi Milan
declared completion Feb 2025 · H Rishabraj Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026