Mumbai/Project record

MahaRERA · the public record

TANISHQ REGENCY

KANNAMWAR NAGAR · KUNAL OMKARA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900015010

Delivery and registration

When is the project declared for completion?

TANISHQ REGENCY is registered with MahaRERA as P51900015010 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900015010
Registered on22 Jan 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TANISHQ REGENCY record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kunal Omkara Developers is the promoter of record on 25 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

25projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TANISHQ REGENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
TANISHQ REGENCY1G+1531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtCOMS/16667/20222022Pending

Location, Land & Connectivity

Located at KANNAMWAR NAGAR, AATMARAM SURVE MARG, Ward GNorth, Mumbai City, 400083. Per the filed land record, the plot is bounded to the north by BALWADI NALLAH, to the south by BY DAYAGHAR CHS LTD, to the east by NALLAH and to the west by 18 30 MTS ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Andheri MIDC / SEEPZ7 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district17 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vikhroli East

Shree Balaji 7
possession by Sep 2026 · Saptrishi Landmarks LLP
Unique Enclave Residency
possession by Sep 2026 · Fazal Shaikh
Vrindavan Elite
possession by Oct 2026 · Matrix Constructions
Meadows 83
possession by Oct 2026 · Shreeji Realtors
Eastern Groves Phase 2
possession by Dec 2026 · VL Savli Developers LLP
GS Casa
possession by Dec 2026 · Prach Realcon LLP

Major developers building in Vikhroli East

Other RERA-registered projects in Mumbai City

Tarabaug
possession by Dec 2032 · Darshan Developers
Tejal
declared completion Mar 2026 · UHP Developers & Consultants
Temple Avenue
possession by Dec 2029 · Ratnaraj Alliance LLP
Terraces Forjett Hill
possession by Sep 2027 · Suparshva Incorporation
The Address By GS Sion Tower A
possession by Jul 2031 · Ten X Realty Limited
The Address By GS Sion Tower B
possession by Jul 2031 · Ten X Realty Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026