MahaRERA Property Intelligence · Thane

THAKARE COMPLEX

P51700022578 · AMBERNATH · promoter Shreeji Developers

Certificate SignedDue 30 May 2025

Delivery & Registration

MahaRERA registrationP51700022578
Registered on07 Oct 2019
Promoter-declared completion30 May 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shreeji Developers is the promoter of record on 141 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
THAKARE COMPLEX - A WING1G+631 Dec 2022
THAKARE COMPLEX - B WING1G+331 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202330 May 2025DUE TO COIVD ALL THE CONSTRUCTION WORK HAS BEEN STOPPED FOR MORE THAN 12 MONTHS AND ALSO DUE TO RECESSION IN CONSTRUCTION, SHORTAGE OF LABOURS & MATERIAL, WE ARE NOT ABLE TO MOVE C

Location, Land & Connectivity

Located at AMBERNATH, JAVSAI, AMBERNATH , Ambarnath, Thane, 421502. Per the filed land record, the plot is bounded to the north by 24 MT DP ROAD, to the south by S NO 1 AND H NO 6, to the east by S NO 2 AND H NO 2 and to the west by S NO 2 AND 3 MT ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreeji Developers is the promoter on 22 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shreeji Developers project & its RERA track record →

Other flagged projects by Shreeji Developers

Shreeji Developers
FlaggedRaigarh
Shreeji Developers
FlaggedRaigarh
Shreeji Developers
FlaggedMumbai Suburban
Shreeji Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Ambernath

Sky Gardens At Godrej Vihaa
possession by Sep 2026 · K. R. Real Estate Pvt. Ltd.
Sudama Elevate
possession by Dec 2026 · Sudam Zipa Rasal
Shree Ram Kutir
possession by May 2027 · Shreeram Realty
Vasudev Valley, Jamdare Heights
Not filing quarterly progress reports · possession by Mar 2028 · Ravindra Hari Gaikwad
Patels Pristine
possession by Jun 2031 · Sahajanand Developers
Godrej Vihaa Phase 5
Not filing quarterly progress reports · possession by Dec 2031 · K. R. Real Estate Pvt. Ltd.

Major developers building in Ambernath

Other RERA-registered projects in Thane

Thakker Shraddha Kunj
possession by Dec 2026 · M/s Thakker World Constructions LLP
Thana Co-Op Housing Society Sopan
declared completion Dec 2021 · Aditya Associates
Thane Project
possession by Jul 2029 · Lodha Developers Limited
Thane Shivam Chs Ltd
possession by Dec 2026 · Mahesh Shriram Borkar
Thanekar BKC Paramount
possession by Dec 2028 · Thanekar Realtor LLP
Thanekar BKC Vista
possession by May 2029 · Thanekar Realtor LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026