Mumbai/Project record

MahaRERA · the public record

TWINS TOWER

Thane · UNIQUE BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700009588

Delivery and registration

When is the project declared for completion?

TWINS TOWER is registered with MahaRERA as P51700009588 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700009588
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TWINS TOWER record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Unique Builders Developers is the promoter of record on 133 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

133projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TWINS TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
B11G+831 Dec 2020
B21G+631 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Due to scarcity of Labour & Material in Covid Period our construction work was stopped for 6 to 8 months.

Location, Land & Connectivity

Located at Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by PROPERTY OF SHRI KALURAM VALAKU PATIL, to the south by PROPERTY OF D G GHULE, to the east by PROPERTY OF SHRI NAMDEV VALAKU PATIL and to the west by ROAD AND BOUDARY OF MHARAL PADA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park33 km
Andheri MIDC / SEEPZ36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)39 km
Lower Parel / Worli business district47 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Unique Builders & Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Tycoons Orbis
possession by Dec 2026 · M/s. Tycoons Developers
Tycoons Square Avenue I Tower A
declared completion Jul 2025 · Tycoons Avanti Projects Pvt. Ltd.
Tycoons Square Avenue I Tower B
possession by Jun 2027 · Tycoons Avanti Projects Pvt. Ltd.
Tycoons Square Avenue I Tower C
possession by Jun 2027 · Tycoons Avanti Projects Pvt. Ltd.
Tycoons Square Avenue I Tower E-F
declared completion Oct 2025 · Tycoons Avanti Projects Pvt. Ltd.
Tycoons Square Avenue III Tower C
declared completion Jun 2025 · Tycoons Avanti Projects Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026