MahaRERA Property Intelligence · Thane

Tycoons Square Avenue I Tower E-F

P51700023429 · Chikanghar · promoter Tycoons Avanti Projects

Certificate SignedDue 30 Oct 2025

Delivery & Registration

MahaRERA registrationP51700023429
Registered on12 Dec 2019
Promoter-declared completion30 Oct 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tycoons Avanti Projects is the promoter of record on 9 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Tower E1G+231 Oct 2024
Tower F1G+231 Oct 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Chikanghar, Birla College Road, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by 18 Mtr Wide Road, to the south by 6 Mtr Wide Road, to the east by 15 Mtr Wide D P Road and to the west by S No 12. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tycoons Avanti Projects Pvt. Ltd. is the promoter on 7 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Tycoons Avanti Projects Pvt. Ltd.

Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
Not filing quarterly progress reportsThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane

Other RERA-registered projects in Kalyan

Tharwani Solitaire Phase IV
possession by Jul 2026 · Anil Hardasmal Tharwani
Kailash Gardens
possession by Jul 2026 · Shree Laxmi Enterprises
Mangeshi Ambar
possession by Jul 2026 · Mangesh Dashrath Gaikar
Mangeshi Tulip
possession by Jul 2026 · Mangesh Dashrath Gaikar
Anand 21 Uptown
possession by Aug 2026 · VPA Developers
Pawan Atharva Phase I
possession by Aug 2026 · Pawan Real Estate

Major developers building in Kalyan

Other RERA-registered projects in Thane

Tycoons Square Avenue III Tower C
declared completion Jun 2025 · Tycoons Avanti Projects Pvt. Ltd.
Tycoons Square Avenue III Tower D
possession by Dec 2026 · Tycoons Avanti Projects Pvt. Ltd.
Tycoons Valley Tower A
declared completion Dec 2025 · M/s. Milestone Space
Tycoons Valley Tower B
declared completion Jun 2025 · M/s. Milestone Space
Type-B Redwood
declared completion Dec 2022 · RDC Ventures
Udaynagar Chs
possession by Mar 2028 · Natu Paranjape Realty

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026