MahaRERA Property Intelligence · Mumbai Suburban

UK SANGFROID

P51800007085 · Andheri West · promoter Keemaya Build Private

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP51800007085
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Keemaya Build Private is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
UK Sangfroid1G+2231 Dec 2019

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000001217528/11/2017A L DEOKAR vs Devanshu bansalorder passed
CC00600000019621530/06/2021Ganpatrao Appa Jadhav vs 1.The Vaidehi-Akash Housing Pvt. ltd. 2. The Keemya Build Pvt. Ltd.order passed
CC00600000019566118/01/2021PRAMOD INDERMALJI BANDI vs KEEMAYA BUILD PRIVATE LTDorder passed
CC00600000039638822/06/2023Ankit Desai vs Keemaya Build Pvt Limitedorder passed
CC00600000048004513/04/2024KEEMAYA BUILD PRIVATE LIMITED vs Mr. Nitin S. Deshpandeorder passed
CC00600000048021330/04/2024KEEMAYA BUILDERS PRIVATE LIMITED vs Mr. Nitin S Deshpandeorder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Consumer Disputes Redressal Forum Mumbai Suburban DistrictCC 1702014Ongoing The Said Litigation Does Not Affect The Project In Any Case And There Is No Injunction Or In
Consumer Disputes Redressal Forum Mumbai Suburban DistrictCC 1712014Ongoing The Said Litigation Does Not Affect The Project In Any Case And There Is No Injunction Or In
State Consumer Disputes Redressal Commission MaharashtraCC 1882017Ongoing The Said Litigation Does Not Affect The Project In Any Case And There Is No Injunction Or In
The Bombay City Civil Court Borivali Division12762016Ongoing The Said Litigation Does Not Affect The Project In Any Case And There Is No Injunction Or In

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Dec 2020We are in a process to obtain an Occupation Certificate.

Location, Land & Connectivity

Located at Andheri West , Azad Nagar, Off link road , Andheri, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by Ushakiran CHS, to the south by Shivalaya Heights, to the east by 9 Metres Wide Road Off Veera Desai and to the west by Andheri Sports Complex. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Bandra Kurla Complex (BKC)8 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Keemaya Build Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Keemaya Build Private Limited

Keemaya Build Private Limited
FlaggedMumbai Suburban
Keemaya Build Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Andheri West

Hubtown Premiere Residences - Bel Air
possession by Jul 2026 · Hubtown Limited
Morya Grand
possession by Jul 2026 · Nakta Investment Pvt. Ltd.
Umang Heights
possession by Aug 2026 · L K Infracon LLP
Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Umang Heights
possession by Aug 2026 · L K Infracon LLP
Umar Park
possession by Jun 2027 · ARY Developers
Umiya Parijat
declared completion Oct 2025 · D.d. Dezines Group
Umiya Residency
declared completion Feb 2024 · M/s Meghji Khimji Developers LLP
Un Named
declared completion Feb 2021 · Sanjay Fakirchand Garg
Unicore Aura
declared completion Dec 2023 · Unicore Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026