Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP51700015800
Registered on26 Mar 2018
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Unnathi Estates is the promoter of record on 21 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
G31G+2331 Dec 2023
G41G+2231 Dec 2023

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000009007211/07/2019Ajay Ashok Ghanghav vs RAUNAK GROUP -UNNATHI WOODS Phase VII-BTHANEorder passed
CC00600000039671617/07/2023UNNATHI ESTATES vs Mrs. Damayanti Jagdish Pujaraorder passed
CC00600000049038806/05/2024UNNATHI ESTATES vs Oyesh Mohammed Afroz Shaikhorder passed
CC00600000059135031/07/2024UNNATHI ESTATES vs Mr. Vaibhav S. Raskarorder passed
CC00600000059135131/07/2024UNNATHI ESTATES vs Mr. Shreyas Shivdikarorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Thane Civil Court2572014Pending
Thane Civil Court383/20162016Pending

Location, Land & Connectivity

Located at KAVESAR, G. B. ROAD THANE, Mumbai, Mumbai Suburban, 400615. Per the filed land record, the plot is bounded to the north by S NO 245-3, to the south by PARK RESERVATION, to the east by S NO 248 30 MTR D P ROAD and to the west by BOUNDARY OF VILLAGE VADAVALI. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park20 km
Andheri MIDC / SEEPZ21 km
Chhatrapati Shivaji Int'l Airport24 km
Bandra Kurla Complex (BKC)26 km
Lower Parel / Worli business district35 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Unnathi Estates is the promoter on 7 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Unnathi Estates

Other RERA-registered projects in Owale

ACE Aristo
possession by Oct 2026 · Gaurav Land Corporation
Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Puranik Home Town - E
possession by Dec 2026 · Puranik Builders Limited
Vihang Plaza - A Commecial
possession by Dec 2026 · Vihang Enterprises
Vihang Woods
possession by Dec 2026 · Vihang Enterprises
Ace Enclave
possession by Dec 2026 · Ace Signature Homes LLP

Major developers building in Owale

Other RERA-registered projects in Thane

Unnathi Woods Phase Viii
possession by Dec 2027 · Unnathi Estates
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Upper Thane - Ecopolis A
declared completion Sep 2022 · Lodha Developers Limited
Upper Thane Ecopolis A - B
declared completion Sep 2022 · Lodha Developers Limited
Upper Thane - Eden D
possession by Mar 2028 · Lodha Developers Limited
Upper Thane - Eden E
possession by May 2027 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026