MahaRERA · the public record
USHAKIRAN ENCLAVE
BEHIND SHANKESHWAR NAGAR · JAYANT ENTERPRISES
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700028914
Delivery and registration
When is the project declared for completion?
USHAKIRAN ENCLAVE is registered with MahaRERA as P51700028914 and the promoter has declared completion for 31 Dec 2028.
31 Dec 2028
declared completion
27months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700028914 |
| Registered on | 12 Apr 2021 |
| Promoter-declared completion | 31 Dec 2028 |
| Current status | Certificate Signed |
| Against today | 27 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for USHAKIRAN ENCLAVE record 20 quarterly progress reports since registration.
20quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Jayant Enterprises is the promoter of record on 51 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
51projects
registered with MahaRERA
3flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In USHAKIRAN ENCLAVE, ₹17.24 Cr of a declared ₹34.52 Cr estimated project cost is reported as incurred, about 49.9%, as at the last certified filing with MahaRERA.
49.9%
₹17.24 Cr
of ₹34.52 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In USHAKIRAN ENCLAVE, 62 of 112 homes filed with MahaRERA are recorded as sold or booked (58 with registered agreements and 4 booked), about 55%, and 50 remain available.
55%sold
62 of 112 homes
₹21.68 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹18.51 Cr (about 85%) is recorded as collected and ₹3.17 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 62 registered agreements, the effective carpet rate is ₹8,233/sqft, with eight in ten falling between ₹4,221 and ₹10,567 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 18 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 62 homes carry one, and 50 of the 112 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 109 | 388 sqft | Rs 31.73 lakh typical, over Rs 15.95 lakh to Rs 44.00 lakh | 52 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In USHAKIRAN ENCLAVE, every one of the 50 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 112 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| USHAKIRAN ENCLAVE | 1 | G+13 | 112 | - |
Unit mix on the filing: 112 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2028 | The completion of the project is getting delayed as we intend to revise the sanctioned plan for the extension of the existing building by the addition of further floors. Since the |
Location, Land & Connectivity
Located at BEHIND SHANKESHWAR NAGAR, NANDIVALI PANCHANDA, Thane, Thane, 421203. Per the filed land record, the plot is bounded to the north by S NO 18, to the south by S NO 21 H NO 2 AND S NO 71, to the east by S NO 71 EXISTING ROAD and to the west by S NO 71. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 21 km |
| Andheri MIDC / SEEPZ | 24 km |
| Chhatrapati Shivaji Int'l Airport | 26 km |
| Bandra Kurla Complex (BKC) | 27 km |
| Lower Parel / Worli business district | 35 km |
| Nariman Point / Fort | 41 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.