Mumbai/Project record

MahaRERA · the public record

V KANTA

KOLSHET · TARANG DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

138units filed as unsoldInventory · 18 September 2026
31 Dec 2032declared completionMahaRERA registration · read 10 Sep 2026
70registered unitsMahaRERA registration · read 10 Sep 2026

The record · free to read

Registration read 10 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2032

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 10 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1330002601632

Delivery and registration

When is the project declared for completion?

V KANTA is registered with MahaRERA as PM1330002601632 and the promoter has declared completion for 31 Dec 2032.

31 Dec 2032

declared completion

75months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 10 Sep 2026

MahaRERA registrationPM1330002601632
Registered on24 Aug 2026
Promoter-declared completion31 Dec 2032
Current statusCertificate Signed
Against today75 months to the declared date

Promoter record

What else is this promoter on record for?

Tarang Developers is the promoter of record on 12 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 10 Sep 2026

Sales

How much has actually been sold?

In V KANTA, 0 of 138 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 138 remain available.

0%sold

0 of 138 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 10 Sep 2026

The inventory filing also declares: 13 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for V KANTA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

No home in V KANTA carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 138 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 6,122 a sq ft typical, over Rs 6,122 to Rs 7,674.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 138 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 138 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 70 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING 11G+732-
BUILDING 23G+1038-

Unit mix on the filing: 147 residential and 4 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KOLSHET, KOLSHET ROAD, Thane, Thane, 400607. Per the filed land record, the plot is bounded to the north by 11, to the south by 11, to the east by 11 and to the west by 11. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kolshet

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Kolshet

Other RERA-registered projects in Thane

V. M. Heights
declared completion Dec 2022 · Swayam Developers
Vadlakonda Apartment
declared completion Dec 2025 · S S Developers
Vagheshwari Developers
declared completion Dec 2022 · Aashu Laxman Mungesh
Vaibhav Serenity - Wing D
possession by Apr 2028 · Vaibhav Siddhi Construction CO
Vaikunth Cluster 2
declared completion Dec 2024 · Pepl Developers Pvt Ltd
Vaikunth Cluster 3 T1
possession by Jun 2027 · Pepl Developers Pvt Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026