MahaRERA Property Intelligence · Thane

VADLAKONDA APARTMENT

P51700033995 · PADMANAGAR · promoter Developers

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51700033995
Registered on17 Mar 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
VADLAKONDA APARTMENT1G+731 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PADMANAGAR, 0, Bhiwandi, Thane, 421302. Per the filed land record, the plot is bounded to the north by PLOT BEARING S NO 34 P, to the south by PLOT BEARING S NO 34 P, to the east by DP ROAD and to the west by DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~25 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park25 km
Andheri MIDC / SEEPZ26 km
Chhatrapati Shivaji Int'l Airport30 km
Bandra Kurla Complex (BKC)32 km
Lower Parel / Worli business district40 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

S S Developers is the promoter on 13 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by S S Developers

S S Developers
Past its declared completion dateThane
S S Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Bhiwandi

Neelkanth Sadan
possession by Jul 2026 · Shreeji Enterprises
Hill Spring
possession by Aug 2026 · Asha Infratech
Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Vaibhav
declared completion Jun 2025 · Gavdevi Shelter
Vaibhav Horizon
declared completion Sep 2023 · Vaibhav Siddhi Construction Co.
Vaibhav Serenity - Wing D
possession by Apr 2028 · Vaibhav Siddhi Construction CO
Vaibhavi City
declared completion Dec 2022 · Pradip Ganpat Pawar
Vaibhavi City B-2
declared completion Dec 2024 · Vaibhavi Developers
Vaijnath
declared completion Dec 2018 · Prakash Lele Construction

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026