41units filed as unsoldInventory · 13 September 2026
30 Jan 2028declared completionMahaRERA registration · read 12 Jul 2026
177registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700012319

Delivery and registration

When is the project declared for completion?

UTSAV is registered with MahaRERA as P51700012319 and the promoter has declared completion for 30 Jan 2028.

30 Jan 2028

declared completion

16months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700012319
Registered on01 Sep 2017
Promoter-declared completion30 Jan 2028
Current statusCertificate Signed
Against today16 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for UTSAV record 32 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 32 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In UTSAV, ₹47 of a declared ₹95 estimated project cost is reported as incurred, about 49.0%, as at the last certified filing with MahaRERA.

49.0%

₹47

of ₹95 declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In UTSAV, 85 of 126 homes filed with MahaRERA are recorded as sold or booked (68 with registered agreements and 17 booked), about 67%, and 41 remain available.

67%sold

85 of 126 homes

₹29

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹18 (about 61%) is recorded as collected and ₹11 as receivable. The project registers 177 homes in total, while this sold/unsold inventory filing covers 126 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 51 not for sale.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 85 homes carry one, and 41 of the 177 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
C301392 sqftRs 0.00 lakh typical, over Rs 0.00 lakh to Rs 0.00 lakh31 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In UTSAV, 39 of the 41 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 40 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 177 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Utsav Wing A1G+127115 Nov 2021
Utsav Wing B1G+137015 Nov 2021
Utsav Wing C1G+21815 Nov 2021
Utsav Wing D1G+21815 Nov 2021

Unit mix on the filing: 177 residential.

Legal and disputes

What disputes are disclosed?

43 complaints are on the MahaRERA record for UTSAV, with orders passed in 31 of them.

43complaints

31with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000133916/10/2017Sajan Jose Padikkala vs Ashok Chatumal Gacheriaorder passed
CC00600000001202023/11/2017Rajive Thampy vs Ashok Chatumal Gacheriaorder passed
CC00600000029259315/09/2022ADDON EXPORT HOUSE LIMITED vs TULIP LAND & DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000030358805/12/2022M/S. COCOATEASE vs TULIP LAND AND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000030358505/12/2022APD EXPORTS vs TULIP LAND AND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000030358605/12/2022MOHIT VIJAY KHILNANI vs TULIP LAND AND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000030358705/12/2022MOHIT VIJAY KHILNANI vs TULIP LAND AND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000034424807/02/2023Sadanand babarbhai keni vs Clublife Realtors Private Limitedorder passed
CC00600000037482518/03/2023Amita Dinesh Sawant vs Club life Realtors Pvt.Ltdorder passed
CC00600000037482618/03/2023Amita Dinesh Sawant vs Club Life Realtors Pvt.Ltdorder passed
CC00600000039587420/05/2023Lathish RK vs M/s.Club Life Realtors Pvt Ltdorder passed
CC00600000039653403/07/2023Mr Ramesh Premaney vs Club Life realtors Pvt Ltdorder passed
CC00600000039653503/07/2023Mr Harish Awtaney vs Club Life Realtors Pvt Ltdorder passed
CC00600000039662207/07/2023Mr Jaikishan Chimandas Adtani vs Club Life Realtors Pvt Ltdorder passed
CC00600000039664609/07/2023Mrs Madhu Kishor Bulchandani vs Club Life Realtors Pvt Ltdorder passed
CC00600000039664709/07/2023Mr Chander Prakash Kewlani vs Club Life Realtors Pvt Ltdorder passed
CC00600000039684102/08/2023SONI TARAK SHAH vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC00600000039692002/08/2023SONI TARAK SHAH vs CLUBLIFE REALTORS PVT LTDorder passed
CC00600000039692103/08/2023SONI TARAK SHAH vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC00600000039707814/08/2023Chandini Devnani vs Club Life Realtors Pvt Ltdorder passed
CC00600000039707914/08/2023Chandini Devnani vs Club Life Realtors Pvt Ltdorder passed
CC00600000039709314/08/2023Chandini Devnani vs Club Life Realtors Pvt Ltdorder passed
CC00600000039731231/08/2023GUNASEELAN BALAKRISHNAN vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC00600000039731331/08/2023GUNASEELAN BALAKRISHNAN vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC00600000039728516/09/2023Tanpreet Marwah vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC00600000039731431/08/2023Soni Gunaseelan vs Club Life Relators Pvt Ltdpending / no order on file
CC00600000039738416/09/2023MEENA BHAGAT vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC00600000039754327/09/2023MAHESH JAYANTILAL PATEL vs CLUB LIFE REALTORS PVT LTDorder passed
CC00600000040823118/12/2023Mukesh Anand vs Club Life Realtors Private Limited and Hive Carbon-Zero Developerspending / no order on file
CC00600000042955708/03/2024Utsav Association of Allottees vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC00600000042955812/03/2024PRAKASH RANCHODDAS PATANI vs Club Life Realtors Pvt. Ltd.order passed
CC00600000048019601/05/2024SHADMAN SHARIF AHMED KUDCHIKAR vs CLUB LIFE REALTORS PRIVATE LIMITEDorder passed
CC00600000048019701/05/2024SHADMAN SHARIF AHMED KUDCHIKAR vs CLUB LIFE REALTORS PRIVATE LIMITEDorder passed
CC1250076506/03/2025Lalit Hemant Samant vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC1250337121/09/2025Kailash Naresh Sidhwa vs CLUBLIFE REALTORS PRIVATE LIMITEDorder passed
CC1250420128/11/2025Hitesh Jethwani vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC1250420428/11/2025Amit Awtaney vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC1250454220/12/2025APD Exports vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC1250457322/12/2025Cocoatease Cocoatease vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC1250457622/12/2025Kanchan Khilnani vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC1250460624/12/2025Vijay Kalyan Khilnani vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file
CC1260260004/05/2026Umesh Narsaiah Annam vs Sagar Macchapending / no order on file
CC1260208709/04/2026VINOD BIYANI LIMITED vs CLUBLIFE REALTORS PRIVATE LIMITEDpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered14 Nov 2023Due to lock down the workers and construction work is slow down.
14 Nov 202330 Jan 2028CHANGE IN MANAGEMENT AND FRAUD COMMITTED BY EARLIER MANAGMENT.

Location, Land & Connectivity

Located at Bhiwandi, Bhiwandi (M Corp.), Bhiwandi, Thane, 421302. Per the filed land record, the plot is bounded to the north by SURVEY NO 85, to the south by PIPELINE BHADWAD ROAD, to the east by SURVEY NO 925 93 AND SURVEY NO 80 BY and to the west by SURVEY NO 92 -1 BHADWAD LAKE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~24 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park24 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport29 km
Bandra Kurla Complex (BKC)30 km
Lower Parel / Worli business district39 km
Nariman Point / Fort46 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

V-10 Lake View
possession by Dec 2027 · V TEN Realty Private Limited
V A Business Centre
possession by Dec 2027 · Shradhha Saburi Associates
V Kanta
possession by Dec 2032 · Tarang Developers
V. M. Heights
declared completion Dec 2022 · Swayam Developers
Vadlakonda Apartment
declared completion Dec 2025 · S S Developers
Vagheshwari Developers
declared completion Dec 2022 · Aashu Laxman Mungesh

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.