Mumbai/Project record

MahaRERA · the public record

VANGANI DARSHAN PHASE 1

Karav Village · Panika Infrastructures Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700003380

Delivery and registration

When is the project declared for completion?

VANGANI DARSHAN PHASE 1 is registered with MahaRERA as P51700003380 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700003380
Registered on05 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VANGANI DARSHAN PHASE 1 record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VANGANI DARSHAN PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A11G+4-
A21G+4-
A31G+4-
C1G+4-
B1G+4-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for VANGANI DARSHAN PHASE 1, with orders passed in 5 of them.

7complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005583117/08/2018PAWAN GHANSHYAM GOPLANI vs PANIKA INFRASTRUCTURE PVT. LTD.order passed
CC1240043016/10/2024Premkumar Lalsingh Pathare vs Panika Infrastructures Pvt. Ltd.order passed
CC1240047219/10/2024Doreen Loraine Moniz vs Panika Infrastructures Pvt. Ltd.order passed
CC1240055924/10/2024Gaurav Suryakant Lohar vs Panika Infrastructures Pvt. Ltd.order passed
CC1240055724/10/2024Baburao Dashrath Wankhede vs Panika Infrastructures Pvt. Ltd.order passed
CC1260141414/03/2026Vishwas Jainwal vs Panika Infrastructures Pvt. Ltd.pending / no order on file
CC1260141714/03/2026ANWAR ABDUL RAZAK SHAIKH vs Panika Infrastructures Pvt. Ltd.pending / no order on file

Location, Land & Connectivity

Located at Karav Village, Karav Rd., Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by ROAD, to the south by G NO 3, to the east by G NO 2 REMAINING and to the west by G NO 1 . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~43 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park43 km
Andheri MIDC / SEEPZ47 km
Bandra Kurla Complex (BKC)47 km
Chhatrapati Shivaji Int'l Airport47 km
Lower Parel / Worli business district53 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Jagannath Paradise
possession by Sep 2026 · Mayur Group
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Krishna Sudama Residency
possession by Sep 2026 · SAI Homes
MAA Bhawani Empire
Deregistered by MahaRERA · possession by Sep 2026 · MAA Bhawani Construction
Raghu Anand Villa
possession by Sep 2026 · United Developers

Other RERA-registered projects in Thane

Vanya Arcade
possession by Jun 2027 · R A Infrastructure
Varad Ashish
declared completion May 2026 · Varad Realtors
Varad Vinayak Complex Building C
possession by Dec 2027 · Shree Balaji Builders & Developers
Varada Heights
declared completion Oct 2022 · Surendra Motiram Mhatre
Vardhaman Enclave
possession by Dec 2026 · Vardhaman Builders
Vardhaman Kutir
declared completion Dec 2023 · Vardhaman Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026