Mumbai/Project record

MahaRERA · the public record

VARUN VILLA

BADLAPUR · MAHARASHTRA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700016837

Delivery and registration

When is the project declared for completion?

VARUN VILLA is registered with MahaRERA as P51700016837 and the promoter has declared completion for 30 Sep 2018.

30 Sep 2018

declared completion

96months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700016837
Registered on18 Jun 2018
Promoter-declared completion30 Sep 2018
Current statusCertificate Signed
Against todayabout 96 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARUN VILLA record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Maharashtra Developers is the promoter of record on 66 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

66projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VARUN VILLA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
VARUN VILLA1G+530 Sep 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BADLAPUR, SURVEY NO 67 HISSA NO 3 PLOT NO 6, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by SURVEY NO 67 BY 3 PLOT NO 5, to the south by SURVEY NO 67 BY 3 PLOT NO 6 P, to the east by SURVEY NO 5 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Maharashtra Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Maharashtra Developers

Maharashtra Developers
FlaggedThane

Other RERA-registered projects in Badlapur

Jagannath Paradise
possession by Sep 2026 · Mayur Group
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Krishna Sudama Residency
possession by Sep 2026 · SAI Homes
MAA Bhawani Empire
Deregistered by MahaRERA · possession by Sep 2026 · MAA Bhawani Construction
Raghu Anand Villa
possession by Sep 2026 · United Developers

Other RERA-registered projects in Thane

Varun Vista
possession by Dec 2028 · Not Available
Vasani Dream City
possession by Dec 2031 · Vasani Enterprises LLP
Vasant Springwoods Phase 2
declared completion Jun 2019 · M/S Shree Constructions
Vasant Vastu
declared completion Dec 2022 · SAI Sadguru Builders & Developers
Vasant Vatika
declared completion Oct 2025 · OM Constructions
Vastu Anand
declared completion Jun 2025 · Shree Ekdant Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026