VASANT VASTU

Thane · SAI SADGURU BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700014193

Delivery and registration

When is the project declared for completion?

VASANT VASTU is registered with MahaRERA as P51700014193 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700014193
Registered on14 Nov 2017
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VASANT VASTU record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Sadguru Builders is the promoter of record on 120 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

120projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VASANT VASTU in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
VASANT VASTU1G+2030 Jun 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for VASANT VASTU, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000058089808/07/2024OMPRAKASH RAMAVADH MAURYA vs OMPRAKASH MAURYAorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2022Due to pandemic situation and subsequent lock downs practically the project was stopped . As per the change in dc rules we got permission offer additional six floor in month of Ju

Location, Land & Connectivity

Located at Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by Tata Power Line, to the south by S No 118, to the east by S No 116 and to the west by Hissa No 4A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ31 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan East

Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Krishna Glory
possession by Oct 2026 · Tulsi Kimaya Construction
Trimurti Garden
possession by Dec 2026 · SAI Narayan Developers
Rai S Aaragya
possession by Dec 2026 · RAI Residency Private Limited
Rai S Heaven
possession by Dec 2026 · RAI Residency Private Limited

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Vasant Vatika
declared completion Oct 2025 · OM Constructions
Vastu Anand
declared completion Jun 2025 · Shree Ekdant Enterprises
Vastu Arcade
declared completion Dec 2021 · Shree Vastu Builders
Vastu Developers
possession by Dec 2026 · Vastu Developers
Vastu Heritage
possession by Dec 2026 · Minakshi Developers
Vastu Homes
possession by Aug 2029 · Siddhivinayak Group

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026