VASANT VASTU

P51700014193 · promoter Sai Sadguru Builders

Certificate SignedDue 31 Dec 2022

Delivery & Registration

MahaRERA registrationP51700014193
Registered on14 Nov 2017
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sai Sadguru Builders is the promoter of record on 114 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
VASANT VASTU1G+2030 Jun 2021

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000058089808/07/2024OMPRAKASH RAMAVADH MAURYA vs OMPRAKASH MAURYAorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202131 Dec 2022Due to pandemic situation and subsequent lock downs practically the project was stopped . As per the change in dc rules we got permission offer additional six floor in month of Ju

Location, Land & Connectivity

Located at Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by Tata Power Line, to the south by S No 118, to the east by S No 116 and to the west by Hissa No 4A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ31 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan East

Krishna Square
possession by Jul 2026 · Gopal Krishna Developers
SAI Heights
possession by Aug 2026 · Aaradhana Construction
Avighna Karan Wing C
possession by Aug 2026 · Avighna Karan
Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Durga Imperial
possession by Oct 2026 · G K Mali & C K Mali

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Vasant Vatika
declared completion Oct 2025 · OM Constructions
Vasant Vihar
declared completion Dec 2019 · Jaideep Construction
Vasind Lifestyle
possession by Dec 2027 · Goranath Estate Private Limited
Vastu Amikumbh
possession by Jul 2028 · M/S Vastu Realty
Vastu Anand
declared completion Jun 2025 · Shree Ekdant Enterprises
Vastu Developer
declared completion Feb 2021 · Vastu Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026