Mumbai/Project record

MahaRERA · the public record

Virmati Villa CHS Ltd

Mumbai Suburban · Shamik Enterprises Pvt Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800001564

Delivery and registration

When is the project declared for completion?

Virmati Villa CHS Ltd is registered with MahaRERA as P51800001564 and the promoter has declared completion for 29 Dec 2020.

29 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001564
Registered on28 Jul 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Virmati Villa CHS Ltd record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shamik Enterprises is the promoter of record on 11 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Virmati Villa CHS Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Shamik Esteem1G+1530 Jun 2019

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Virmati Villa CHS Ltd, with orders passed in 0 of them.

5complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019626805/03/2021PAYAL L. HIRANI vs SHAMIK ENTERPRISES PVT. LTD.pending / no order on file
CC00600000019627105/03/2021REENA J. HIRANI vs SHAMIK ENTERPRISES PVT. LTD.pending / no order on file
CC00600000019655230/03/2021DOMINIC FERNANDES & MATILDA FERNANDES vs SHAMIK ENTERPRISES PVT. LTD.pending / no order on file
CC00600000019655430/03/2021DIOGO MARIO DSOUZA & HARSHA DIOGO DSOUZA vs SHAMIK ENTERPRISES PVT. LTD.pending / no order on file
CC00600000019655830/03/2021D. B. INFRATECH vs SHAMIK ENTERPRISES PVT. LTD.pending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020The project is registered in MahaRERA vide registration No. P51800001564. The proposed date of completion as per RERA registration is 30/06/2019. The development work of "Virmati

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400103. Per the filed land record, the plot is bounded to the north by 6 Mt Road, to the south by 9 Mt Road, to the east by Siddhi Sadan CHS Ltd and to the west by C P House. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shamik Enterprises Pvt Ltd. is the promoter on 8 MahaRERA-registered projects, of which 8 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shamik Enterprises Pvt Ltd. project & its RERA track record →

Other flagged projects by Shamik Enterprises Pvt Ltd.

Shamik Enterprises Pvt Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Shamik Enterprises Pvt Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Shamik Enterprises Pvt Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Shamik Enterprises Pvt Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Shamik Enterprises Pvt Ltd.
Developer in insolvency (NCLT)Palghar
Shamik Enterprises Pvt Ltd.
Developer in insolvency (NCLT)Palghar

Other RERA-registered projects in Borivali West

Borivali Madhumas Chsl
possession by Dec 2026 · Aadhunik Developers
Borivali SAI Hill CHS
possession by Dec 2026 · THE Green Venturez Realtors
Empire Fairmont
possession by Dec 2026 · Empire Realty
Maruti Residency
possession by Dec 2026 · OM Construction
Mascarenhas Apartment
Not filing quarterly progress reports · possession by Dec 2026 · SAI Universal Realtors & Developers
NEW Siddharth CO-Operative Housing Society LTD
possession by Dec 2026 · Not Available

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Visawa CHS Ltd
possession by Dec 2028 · Santosh Jayram Anjarlekar
Vishakha Heights AND Vishakha Regency
declared completion Jun 2026 · M/s Keytech
Vishal 2
declared completion Dec 2022 · Prasham Realtors
Vishal Sagar
declared completion Dec 2022 · J R Properties LLP
Vishnu Bhavan Bldg No 4 A Wing Valencia CHS And B Wing Shree Dutt Guru CHS
possession by Apr 2027 · Shree S S Developers Private Limited
Vishram
declared completion Jun 2026 · Jeevandeep Developers

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026