Mumbai/Project record

MahaRERA · the public record

Vistara World

Bhiwandi · Vistara Buildcon

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

176units filed as unsoldInventory · 20 September 2026
30 Jun 2029declared completionMahaRERA registration · read 12 Jul 2026
227registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700080973

Delivery and registration

When is the project declared for completion?

Vistara World is registered with MahaRERA as P51700080973 and the promoter has declared completion for 30 Jun 2029.

30 Jun 2029

declared completion

33months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700080973
Registered on11 Sep 2025
Promoter-declared completion30 Jun 2029
Current statusCertificate Signed
Against today33 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vistara World record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vistara Buildcon is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Vistara World, ₹4.23 Lakh of a declared ₹31.39 Cr estimated project cost is reported as incurred, about 0.1%, as at the last certified filing with MahaRERA.

0.1%

₹4.23 Lakh

of ₹31.39 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Vistara World, 0 of 176 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 176 remain available.

0%sold

0 of 176 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 227 homes in total, while this sold/unsold inventory filing covers 176 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 51 owner/investor-held.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vistara World in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in Vistara World carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 227 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 2,685 a sq ft typical, over Rs 2,685 to Rs 2,685.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 227 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 227 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 227 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Tower - 11G+14171-
Tower 2 - Wing - A and Wing - B1G+756-

Unit mix on the filing: 227 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Bhiwandi, S. No.86/1/7 and 87/6/1/C, , Panvel, Raigarh, 421302. Per the filed land record, the plot is bounded to the north by Open Plot, to the south by 9M Wide Road, to the east by Open Plot and to the west by Open Plot. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~32 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park32 km
Andheri MIDC / SEEPZ34 km
Chhatrapati Shivaji Int'l Airport37 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district46 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vistara Buildcon is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Vistara Buildcon

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Vistas
declared completion Jun 2023 · Risha Builders & Developers LLP
Vitrag Orbit
declared completion Dec 2018 · Goldfield Assosciates
Vitthai Anant Plaza
possession by Dec 2026 · Sharad Namdeo Gaikwad
Vitthal Heights
possession by Dec 2027 · Bhoir Developers
Vitthal Rukmini Building
declared completion Mar 2024 · Divine Builders
Vitthal Rukmini Tower
declared completion Mar 2025 · Balaram Vitthal Mali

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026