MahaRERA Property Intelligence · Thane

VRUNDAVAN

P51700003306 · DEVRUNG · promoter Shree Vasturachana Developers

Certificate SignedDue 09 Aug 2024

Delivery & Registration

MahaRERA registrationP51700003306
Registered on05 Aug 2017
Promoter-declared completion09 Aug 2024
Current statusCertificate Signed
Against todayabout 23 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Vasturachana Developers is the promoter of record on 7 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
1-A B WING1G+4-
2- A B WING1G+4-
3- A B WING1G+4-
4- A B WING1G+5-
5- A B WING1G+4-
6- A B WING1G+4-
7-A B WING1G+4-
8-A B WING1G+4-
9-A B WING1G+4-
101G+4-
BUNGLOW1G+2-

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007936607/06/2019Suresh Sukhadev Jadhav vs Shree vasturachana Developersorder passed
CC00600000019386830/08/2020Ravindra Kumar Sharma vs M/S Shree Vasturachana Developersorder passed
CC00600000040858518/01/2024Jayvant Janardhan Amrute vs Shree vaturachana developer and partnerorder passed
CC1250273004/08/2025Vrundavan CHSL (society) vs SHREE VASTURACHANA DEVELOPERSorder passed

A co-operative housing society is the complainant here (Vrundavan CHSL) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202029 Jun 2020APPLICATION HAS BEEN DONE FOR OCCUPANCY CERTIFICATE BUT IT TAKING TO MUCH TIME AND ALSO AMMENDED NA ORDER WITH FOR BALANCE F.S.I. RECEIVED ATTACHED HEREWITH.
30 Jun 201909 Aug 2024We, M/s. Shree Vasturachana Developers, hereby declare the following with respect to the project Vrundavan bearing registration number. P51700003306 registered under MahaRERA. The

Location, Land & Connectivity

Located at DEVRUNG, VILLAGE ROAD NO 340, Panvel, Raigarh, 421302. Per the filed land record, the plot is bounded to the north by 94-21, to the south by GAOTHAN, to the east by 94-17 94-25 and to the west by 94-15 94-35. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~32 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park32 km
Andheri MIDC / SEEPZ34 km
Chhatrapati Shivaji Int'l Airport37 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district46 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Neelkanth Sadan
possession by Jul 2026 · Shreeji Enterprises
Hill Spring
possession by Aug 2026 · Asha Infratech
Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Vrundavan Dham
declared completion Dec 2023 · Shikhar Lifespaces
Vrundavan Heights
possession by Dec 2026 · Maulikrupa Developers
Vrundavan-I
declared completion Jun 2022 · Shree Vastucreation Developers
Vrundavan Park
possession by Dec 2027 · Shree Vastunirman Developers
Vrundavan Park Jaswandi
possession by Jun 2028 · Shree Vastunirman Developers
Vyanktesh Darshan C.h.s
declared completion Oct 2025 · Siddhivinayak Group

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026