Mumbai/Project record

MahaRERA · the public record

Yashashree

Mulund · TRUPTI BUILDCON LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

19units filed as unsoldInventory · 12 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008388

Delivery and registration

When is the project declared for completion?

Yashashree is registered with MahaRERA as P51700008388 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008388
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Yashashree record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 36 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Trupti Buildcon Llp is the promoter of record on 4 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Yashashree, ₹4.11 Cr of a declared ₹13.25 Cr estimated project cost is reported as incurred, about 31.0%, as at the last certified filing with MahaRERA.

31.0%

₹4.11 Cr

of ₹13.25 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 17 homes carry one, and 19 of the 36 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B - 104581 sqftRs 50.88 lakh typical, over Rs 46.25 lakh to Rs 57.66 lakh11 filed on this stack, floors 1–7

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In Yashashree, 11 of the 19 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 18 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
Yashashree1G+24-
Yashashree1G+24-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for Yashashree, with orders passed in 4 of them.

7complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005630524/09/2018Samrat Malpani vs SiroyaFM Constructions Pvt Ltdorder passed
CC00600000019298716/02/2021Abhijit Birjepatil vs M/s Siroya FM Constructions pvt ltdorder passed
CC00600000019835024/09/2021Hirengiri D Goswami & Hemina H Goswami vs M/s Siroyafm Constructions Private Limitedorder passed
CC00600000019835124/09/2021Hirengiri D Goswami & Hemina H Goswami vs M/s Siroyafm Constructions Private Limitedorder passed
CC00600000042896324/01/2024Navghar Mulund Yashashree CHSL and others (society) vs Siroya FM Constructions Pvt. Ltd.pending / no order on file
CC1250262830/07/2025Raju Kumar vs SiroyaFM Constructions Pvt Ltdopending / no order on file
CC1260149618/03/2026Dattatray Parab vs SiroyaFM Constructions Pvt Ltdopending / no order on file

A co-operative housing society is recorded as the complainant (Navghar Mulund Yashashree CHSL and others).

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Mulund CourtSS782/20162016Ongoing
Bombay High CourtCommercial Notice of Motion L no 1031 of 2019 IN Commercial Suit L no 339 of 20192019Disposed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2028Due to limitation of words, reasons and explanations for delay are attached herewith in the application. Please refer the same.

Location, Land & Connectivity

Located at Mulund, Navghar Road, Andheri, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by Road, to the south by Road, to the east by Road and to the west by Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers
Jvms Monica Gardens
possession by Dec 2026 · JVM Spaces

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Yashomati Chsl
declared completion Apr 2026 · Samrat Enterprise
Yashraj Heights
declared completion Nov 2023 · Yashraj Corporation
Yashwant Height
possession by Dec 2026 · M.p. Global Height Private Limited
Yeshwant
possession by Dec 2026 · Shree Krishna Homes PVT LTD
Yeshwant Sadan
possession by Sep 2026 · ARG Life Spaces LLP
YOG Aashray
declared completion Oct 2025 · Gruham Realtors LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026