MahaRERA Property Intelligence · Pune

108 Balaji Crystal

P52100027763 · Near Adi Regency Sai Enclave Road Vijaynagar Kalewadi, Rahatani · promoter Mani Kishanchand Chandiramani

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52100027763
Registered on03 Jan 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Balaji Crystal1G+731 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202431 Dec 2024Reason for delay is due to Financial issues. We are unable to start our construction on site

Location, Land & Connectivity

Located at Near Adi Regency Sai Enclave Road Vijaynagar Kalewadi, Rahatani, Survey no. 108/1/1, Haveli, Pune, 411017. Per the filed land record, the plot is bounded to the north by 18M wide DP Road, to the south by Property of Mr Patil, to the east by 6M wide DP Road and to the west by 7M wide road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rahatani

Adi Amma Insperia
possession by Jul 2026 · J N Realty And Homes
Devkamal Heights
possession by Oct 2026 · MRS Kamal Devram Hole
KK Mangalam Emerald
possession by Oct 2026 · Shah Associates & Properties
AUM Vertex
possession by Dec 2026 · Aum Buildcon
KK Capitol
possession by Dec 2026 · Shah AND Associates
Tamara
possession by Dec 2026 · Goldfinger Kataria Urban Developments

Major developers building in Rahatani

Other RERA-registered projects in Pune

108 Elevate
possession by Dec 2030 · M K Infra
108 Woods
possession by Dec 2030 · Not Available
11 Park Street A Wing
declared completion Jun 2022 · Trimurti Housing
11 Square
possession by Nov 2029 · Varad Developers
11 West
declared completion Dec 2025 · Baner Hills LLP
114 Priyanjali
declared completion Aug 2024 · Rui Universal Realities LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026