MahaRERA Property Intelligence · Pune

212 RIVERWALK

P52100001010 · OPP. BABA KALYANI BUNGALOW · promoter Ramesh Builders (India)

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP52100001010
Registered on25 Jul 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ramesh Builders (India) is the promoter of record on 163 projects, of which 25 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
212 RIVERWALK1G+1731 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Dec 2020We have made applications for various Permissions and NOC's mandatory for application of Completion Certificate, to be issued by various Government/local authorities out of which m

Location, Land & Connectivity

Located at OPP. BABA KALYANI BUNGALOW, LANE NO.3, Pune City, Pune, 411006. Per the filed land record, the plot is bounded to the north by COMMERCIAL BUILDING ON PART OF SUB PLOT NO 59 C, to the south by SUB PLOT NO 59A , to the east by OPEN PLOT NO 30 and to the west by 12M WIDE DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre3 km
Kharadi / EON IT Park4 km
Magarpatta / Hadapsar IT4 km
Pune Int'l Airport (Lohegaon)5 km
Baner–Balewadi belt13 km
Hinjewadi Rajiv Gandhi IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Yerwada

Bluegrass Residences Tower III
possession by Dec 2026 · Sagitarius Ecospaces LLP
Belmont Lunar
possession by Mar 2027 · Prasad Balasaheb Shinde
Vaishnavi Ouranos
possession by Dec 2027 · Vaishnavi & OM Construction
Power Terrace
possession by Mar 2028 · Sapra Builders
River Vista
possession by Mar 2028 · Rahul Shubham LLP
Sheetal Park CO-Operative Housing Society LTD
possession by Mar 2028 · Belvalkar Housing LLP

Major developers building in Yerwada

Other RERA-registered projects in Pune

230/1 Shukrwar Peth
declared completion Sep 2023 · Liyakat Usman Shaikh
233 Nana Peth
declared completion Aug 2023 · Shree Bhawani Constructions
24 Aanand P1
possession by Oct 2028 · Not Available
24 Aanand P2
possession by Apr 2030 · Not Available
24 Carat
declared completion Dec 2020 · ABC AND Mittal Realty
24 Casa Sanjivani
possession by Oct 2027 · Girish Bhaidas Patil

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026