MahaRERA · the public record
41 ESTERA PHASE 3
NEAR SAWATA MALI MANDIR · SAMARTTHA TRIMURTI PROPERTIES
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
05 May 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100019322
Delivery and registration
When is the project declared for completion?
41 ESTERA PHASE 3 is registered with MahaRERA as P52100019322 and the promoter has declared completion for 05 May 2025.
05 May 2025
declared completion
16months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100019322 |
| Registered on | 23 Jan 2019 |
| Promoter-declared completion | 05 May 2025 |
| Current status | Certificate Signed |
| Against today | about 16 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 41 ESTERA PHASE 3 record 26 quarterly progress reports since registration.
26quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Samarttha Trimurti Properties is the promoter of record on 18 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
18projects
registered with MahaRERA
4flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In 41 ESTERA PHASE 3, ₹37.33 Cr of a declared ₹40.10 Cr estimated project cost is reported as incurred, about 93.1%, as at the last certified filing with MahaRERA.
93.1%
₹37.33 Cr
of ₹40.10 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In 41 ESTERA PHASE 3, 147 of 234 homes filed with MahaRERA are recorded as sold or booked (116 with registered agreements and 31 booked), about 63%, and 87 remain available.
63%sold
147 of 234 homes
₹67.57 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹64.76 Cr (about 96%) is recorded as collected and ₹2.81 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 147 registered agreements, the effective carpet rate is ₹7,516/sqft, with eight in ten falling between ₹7,242 and ₹7,745 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 17 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 147 homes carry one, and 87 of the 234 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| D-206 | 620 sqft | Rs 44.90 lakh typical, over Rs 44.63 lakh to Rs 44.90 lakh | 13 filed on this stack, floors 1–14 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In 41 ESTERA PHASE 3, 74 of the 87 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 234 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| D | 1 | G+15 | 124 | - |
| E | 1 | G+15 | 110 | - |
Unit mix on the filing: 234 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 29 Sep 2024 | Out of building D and E promoter has completed building D and will handover the same to allottees well within the timeline of MAHARERA. For building E promoter will required anothe |
| 29 Sep 2024 | 29 Mar 2025 | The project is facing delays due to a severe labor shortage, resulting in the unavailability of skilled workers. Additionally, the contractor's performance has been adversely affec |
| 29 Mar 2025 | 05 May 2025 | Post Facto Extension due to time lag between project completion and OC received. |
Location, Land & Connectivity
Located at NEAR SAWATA MALI MANDIR, PUNAWALE JAMBE ROAD, Mulshi, Pune, 411033. Per the filed land record, the plot is bounded to the north by 41 ESTERA PHASE 1, to the south by REMAINING PROPERTY OF SR NO 41, to the east by 41 ESTERA PHASE 2 and to the west by 12 MTR ROAD. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Pune Junction / city centre | 5 km |
| Baner–Balewadi belt | 7 km |
| Magarpatta / Hadapsar IT | 10 km |
| Pune Int'l Airport (Lohegaon) | 12 km |
| Kharadi / EON IT Park | 12 km |
| Hinjewadi Rajiv Gandhi IT Park | 13 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.