Pune/Project record

MahaRERA · the public record

KOHINOOR SAPPHIRE

VILLAGE TATHAWADE TAL MULSHI, DIST PUNE · RISING ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100022378

Delivery and registration

When is the project declared for completion?

KOHINOOR SAPPHIRE is registered with MahaRERA as P52100022378 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100022378
Registered on16 Sep 2019
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KOHINOOR SAPPHIRE record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rising Associates is the promoter of record on 42 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

42projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KOHINOOR SAPPHIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
A1G+1531 Dec 2023
B1G+1531 Dec 2023
C1G+1631 Dec 2023
D1G+1631 Dec 2023
E1G+1631 Dec 2023
F1G+1631 Dec 2023
G1G+1631 Dec 2023
H1G+1631 Dec 2023
I1G+1631 Dec 2023
MHADA1G+831 Dec 2023

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KOHINOOR SAPPHIRE, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260339403/06/2026Vaibhav Rajendra Musale vs RISING ASSOCIATESpending / no order on file

Location, Land & Connectivity

Located at VILLAGE TATHAWADE TAL MULSHI, DIST PUNE, s no 41/2 and S NO 62/2, Pune City, Pune, 411033. Per the filed land record, the plot is bounded to the north by PART OF SNO 62 2 PART OF S NO 41 2 PART OF S NO 41, to the south by PART OF S NO41 2 PART OF S NO62 2, to the east by S NO 41 2 and to the west by S NO 63 AND REMAINING PART OF S NO 41 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rising Associates is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Rising Associates project & its RERA track record →

Other flagged projects by Rising Associates

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Kohinoor Sapphire II
declared completion Sep 2024 · Rising Associates
Kohinoor Sapphire III
declared completion Feb 2026 · Rising Associates
Kohinoor Satori Mahalunge
possession by Dec 2029 · Intofinity Promoters Private Limited
Kohinoor Shangrila Phase 2
declared completion Dec 2025 · Kohinoor Properties
Kohinoor Uptown Avenue
possession by Dec 2029 · Moonstone Realinfra Private Limited
Kohinoor Viva Pixel- Phase I
declared completion Jun 2026 · Rising Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026