MahaRERA Property Intelligence · Pune

AARAVI

P52100022969 · Erandwane · promoter Kotibhaskar Infrastructures Developers

Certificate SignedDue 14 Oct 2023

Delivery & Registration

MahaRERA registrationP52100022969
Registered on06 Nov 2019
Promoter-declared completion14 Oct 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kotibhaskar Infrastructures Developers is the promoter of record on 30 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
AARAVI1G+1014 Oct 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Erandwane, Pandurang Colony, Haveli, Pune, 411038. Per the filed land record, the plot is bounded to the north by CTS No 157 and CTS No 158, to the south by CTS No 139, to the east by CTS No 138 and to the west by CTS No 139. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kotibhaskar Infrastructures &developers Pvt.ltd. is the promoter on 28 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Kotibhaskar Infrastructures &developers P project & its RERA track record →

Other flagged projects by Kotibhaskar Infrastructures &developers P

Kotibhaskar Infrastructures &developers Pvt.ltd.
FlaggedPune
Kotibhaskar Infrastructures &developers Pvt.ltd.
FlaggedPune
Kotibhaskar Infrastructures &developers Pvt.ltd.
FlaggedPune
Kotibhaskar Infrastructures &developers Pvt.ltd.
FlaggedPune
Kotibhaskar Infrastructures &developers Pvt.ltd.
FlaggedPune
Kotibhaskar Infrastructures &developers Pvt.ltd.
FlaggedPune

Other RERA-registered projects in Kothrud

Umed
possession by Jul 2026 · Runwal Realtors Pvt Ltd
Chandra Apartment
possession by Aug 2026 · Deshpande Landmark Private Limited
Keshar
possession by Aug 2026 · Badhekar Properties
Tungabhadra CO OP HSG SOC
possession by Aug 2026 · Not Available
Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates

Major developers building in Kothrud

Other RERA-registered projects in Pune

Aarcon
declared completion Oct 2025 · Vinod Premchand Chandwani
Aariv Exotica
declared completion Dec 2019 · IK Onkar Constructions
Aarna Hills
declared completion Dec 2024 · Radhe Govind Realtors
Aarna Regency
possession by Jun 2027 · Aarna Associates
Aaroh
declared completion Jan 2023 · Bhide Kulkarni Promoters And Builders
Aaroh Dwelling
declared completion Oct 2022 · Shankar Vithal Beldare AND Others

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026