MahaRERA Property Intelligence · Pune

ANAND RESIDENCY WING B

P52100025791 · Kaniya Park · promoter Kishor Popatlal Tatiya

Certificate SignedDue 31 Dec 2020

Delivery & Registration

MahaRERA registrationP52100025791
Registered on16 Jul 2020
Promoter-declared completion31 Dec 2020
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kishor Popatlal Tatiya is the promoter of record on 11 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
ANAND RESIDENCY WING B1G+531 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kaniya Park, Belthika Nagar, Mulshi, Pune, 411033. Per the filed land record, the plot is bounded to the north by BY A PROPERTY OF MR CHOUBE, to the south by REMAINING LAND AREA OF SAME SURVEY NUMBER, to the east by 6 METER COLONY ROAD and to the west by REMAINING LAND AREA OF SAME SURVEY NUMBER. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Punawale

BVM Flora
possession by Jul 2026 · Sunny Naresh Nagdev
Miracle Mathura
possession by Jul 2026 · Miracle Builders And Developers
Sai Aarav
possession by Jul 2026 · Abhijit Prakash Borase
Samarth Paradise
possession by Aug 2026 · Samarth Associates
Isle OF Life - Building B And C
possession by Aug 2026 · R R Ventures
Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE

Major developers building in Punawale

Other RERA-registered projects in Pune

Anand Sadhan
declared completion Dec 2019 · Sakore Developers LLP
Anand Sagar
possession by May 2036 · Sunshine Associates
Anand Sagar Residency
possession by Mar 2028 · Shripad Builders & Developers
Anand Shree Society
declared completion Apr 2019 · NS Landmarks
Anand Tarang A Building
declared completion Aug 2022 · R K Lunkad Builders AND Promoters
Anand Tarang B1 AND B2
declared completion Jun 2019 · R K Lunkad Builders AND Promoters

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026