MahaRERA Property Intelligence · Pune

ANANDTARA WHITEFIELD RESIDENCES PHASE - I

P52100007529 · LONKAR VASTI · promoter Anandtara Infrastructure

Certificate SignedDue 29 Dec 2020

Delivery & Registration

MahaRERA registrationP52100007529
Registered on17 Aug 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Anandtara Infrastructure is the promoter of record on 8 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
BUILDING C1G+1130 Jun 2019
BUILDING D1G+1130 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202029 Jun 2020We have received revised layout after making changes in Phase II (Rera register No. P52100018257) owing to such changes in the layout we were obliged to intimate the Department of

Location, Land & Connectivity

Located at LONKAR VASTI, MANJARI ROAD, Pune City, Pune, 411036. Per the filed land record, the plot is bounded to the north by SR NO 32 PART, to the south by SR NO 32 CHA 3B PART, to the east by BY 18 MRTS WIDE ROAD SR NO 32 PART and to the west by SR NO 32 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park3 km
Magarpatta / Hadapsar IT3 km
Pune Int'l Airport (Lohegaon)7 km
Pune Junction / city centre8 km
Baner–Balewadi belt18 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anandtara Infrastructure is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Anandtara Infrastructure

Anandtara Infrastructure
FlaggedPune
Anandtara Infrastructure
FlaggedPune
Anandtara Infrastructure
FlaggedPune
Anandtara Infrastructure
FlaggedPune

Other RERA-registered projects in Mundhwa

Moonstone
possession by Aug 2026 · Swamiji Developers
Matoshree Pride
Not filing quarterly progress reports · possession by Aug 2026 · Devidas Suresh Bhat
Shubh Evan C1 Wing
possession by Aug 2026 · Kalash Enterprises
Casa Elanza
possession by Sep 2026 · Parmaz Green Realty LLP
Platinum Capital Office - Phase I
possession by Sep 2026 · A Advani Properties LLP
The Golden Bell
Not filing quarterly progress reports · possession by Dec 2026 · Panchshil Hotels Pvt Ltd

Major developers building in Mundhwa

Other RERA-registered projects in Pune

Anandtara Whitefield Residencies Phase-II
declared completion Feb 2021 · Anandtara Infrastructure
Anandtaras Haritara
declared completion Dec 2019 · Anandtara Properties
Anandvan
declared completion Dec 2023 · Anil Wamanrao Shinde
Anandvan
declared completion Jun 2026 · M/s Skyline Ventures
Anandwan
declared completion Jun 2024 · Viraj Properties
Anandwan Apartment
declared completion Dec 2025 · Rudransh Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026