ATLANTICA EAST WING C D PROJECT

Pune · GAUREE SPACE CREATOR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100012151

Delivery and registration

When is the project declared for completion?

ATLANTICA EAST WING C D PROJECT is registered with MahaRERA as P52100012151 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100012151
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ATLANTICA EAST WING C D PROJECT record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gauree Space Creator is the promoter of record on 94 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

94projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ATLANTICA EAST WING C D PROJECT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
WING C1G+1131 Dec 2023
WING D1G+1131 Dec 2023

Legal and disputes

What disputes are disclosed?

8 complaints are on the MahaRERA record for ATLANTICA EAST WING C D PROJECT, with orders passed in 8 of them.

8complaints

8with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000010635007/01/2022MRS. ALKA SACKLECHA JAIN vs M/S GUAREE SPACE CREATORorder passed
CC00500000010635107/01/2022MRS ANUPAMA ABHISHEK MANTHAPURWAR vs M/S GAUREE SPACE CREATORorder passed
CC00500000010635207/01/2022MR. SUBHASIS DAS vs M/S GAUREE SPACE CREATORorder passed
CC00500000010635307/01/2022MR. PRASHANT DALPATBHAI BAROT vs M/S GAUREE SPACE CREATORorder passed
CC00500000010635407/01/2022MR. PRAVIN AMRUTRAO TATHE vs M/S GAUREE SPACE CREATORorder passed
CC00500000010635507/01/2022MR. SAURABH RAJENDRA KESKAR vs M/S GAUREE SPACE CREATORorder passed
CC00500000010635607/01/2022MR. CHAITANYA CHANDRAKANT DOLAS vs M/S GAUREE SPACE CREATORorder passed
CC00500000017778412/11/2022MEENAKSHI PARADKAR vs GAUREE SAPCE CREATORorder passed

Location, Land & Connectivity

Located at Haveli, Pune, 411036. Per the filed land record, the plot is bounded to the north by MR PHADNEES, to the south by MR ASHOK EKNATH GAIKWAD AND CHAMDIYA AND GOVT ROAD, to the east by PHADNEES and to the west by LUNKAD AND BALASAHEB LONKAR. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park2 km
Magarpatta / Hadapsar IT3 km
Pune Int'l Airport (Lohegaon)6 km
Pune Junction / city centre8 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mundhwa

Casa Elanza
possession by Sep 2026 · Parmaz Green Realty LLP
Platinum Capital Office - Phase I
possession by Sep 2026 · A Advani Properties LLP
The Golden Bell
Not filing quarterly progress reports · possession by Dec 2026 · Panchshil Hotels Pvt Ltd
ACE Villas
possession by Dec 2026 · Jhamtani Realty Private Limited
Anandtara Iris Residences Phase I
possession by Dec 2026 · Anandtara Infrastructure
Anandtara Iris Residences Phase II
possession by Dec 2026 · Anandtara Infrastructure

Major developers building in Mundhwa

Other RERA-registered projects in Pune

Atlantis
declared completion Sep 2020 · Manoj Yeole Ramdas Yeole
Atlantis
declared completion Dec 2024 · Shree Ganesh Developers
Atlantis
possession by Dec 2027 · Atharva Buildwell
Atman Nirvana
possession by Mar 2029 · Shivpriya Realtors LLP
Atrinandan Heights
possession by Dec 2031 · Krushna Developers
Atrium Skyward Wing A
declared completion Jun 2024 · Atrium Homes LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026