BHOOMI BLESSINGS

PUNE · PANKAJ PRAKASH YEOLA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100003641

Delivery and registration

When is the project declared for completion?

BHOOMI BLESSINGS is registered with MahaRERA as P52100003641 and the promoter has declared completion for 30 Sep 2020.

30 Sep 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100003641
Registered on06 Aug 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BHOOMI BLESSINGS record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BHOOMI BLESSINGS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
BHOOMI BLESSINGS BUILDING A1G+731 Mar 2018
BHOOMI BLESSINGS BUILDING B1G+731 Mar 2018
BHOOMI BLESSINGS BUILDING C1G+731 Mar 2018
BHOOMI BLESSINGS BUILDING D1G+7-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for BHOOMI BLESSINGS, with orders passed in 4 of them.

5complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000009590018/08/2021Poonam Tayappa Dhaygude vs Pankaj Prakash Yeolaorder passed
CC00500000009590221/08/2021NIRANJAN DAMODHAR PADAWALE vs PANKAJ PRAKASH YEOLAorder passed
CC00500000009618827/10/2021SHANKAR KISAN CHAKOR vs PANKAJ PRAKASH YEOLA - BHOOMI BLESSINGSorder passed
CC00500000009632708/12/2021SHOBHABAI YOGRAJ LOHAR vs PANKAJ PRAKASH YEOLAorder passed
CC1260241825/04/2026SUHAS S SHETTY vs PANKAJ PRAKASH YEOLApending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2020Delay in completing project
31 Mar 202031 Mar 2020Delay due to labour and material issues

Location, Land & Connectivity

Located at PUNE, -, Haveli, Pune, 411017. Per the filed land record, the plot is bounded to the north by SURVEY NUMBER 71, to the south by SURVEY NUMBER 70, to the east by SURVEY NUMBER 70 hissa 1 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park6 km
Baner–Balewadi belt6 km
Pune Junction / city centre13 km
Pune Int'l Airport (Lohegaon)14 km
Kharadi / EON IT Park17 km
Magarpatta / Hadapsar IT18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pankaj Prakash Yeola is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Pankaj Prakash Yeola project & its RERA track record →

Other flagged projects by Pankaj Prakash Yeola

Pankaj Prakash Yeola
Past its declared completion datePune
Pankaj Prakash Yeola
Registration suspendedPune

Other RERA-registered projects in Rahatani

Devkamal Heights
possession by Oct 2026 · MRS Kamal Devram Hole
KK Mangalam Emerald
possession by Oct 2026 · Shah Associates & Properties
AUM Vertex
possession by Dec 2026 · Aum Buildcon
KK Capitol
possession by Dec 2026 · Shah AND Associates
Tamara
possession by Dec 2026 · Goldfinger Kataria Urban Developments
Aurelia
possession by Dec 2026 · Shitole Properties

Major developers building in Rahatani

Other RERA-registered projects in Pune

Bhoomi Orabelle Phase I
declared completion Dec 2019 · Pankaj Prakash Yeola
Bhoomi Orabelle Phase II
declared completion Dec 2020 · Pankaj Prakash Yeola
Bhoomi Orion
declared completion Dec 2019 · Bhoomi Developers
Bhosale Empire
possession by Dec 2026 · Morus Developers
Bhosale Empire
possession by Dec 2026 · Bhakti Developers
Bhosale Galaxy
possession by Jun 2028 · Bhosale Properties LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026