Pune/Project record

MahaRERA · the public record

BHOOMI ORABELLE PHASE I

- · PANKAJ PRAKASH YEOLA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

05 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

05 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100009798

Delivery and registration

When is the project declared for completion?

BHOOMI ORABELLE PHASE I is registered with MahaRERA as P52100009798 and the promoter has declared completion for 05 Dec 2019.

05 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100009798
Registered on22 Aug 2017
Promoter-declared completion05 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BHOOMI ORABELLE PHASE I record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BHOOMI ORABELLE PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
BHOOMI ORABELLE PHASE I WING A1G+1205 Dec 2018
BHOOMI ORABELLE PHASE I WING B1G+1205 Dec 2018

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for BHOOMI ORABELLE PHASE I, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001139809/04/2018Anil Shukla vs Pankaj Yeolaorder passed
CC00500000005386419/02/2023Devendra Chandrakant Upadhye vs Pankaj Yeolaorder passed
CC00500000006439207/08/2020Kunal vs Mr. Pankaj Prakash Yeolaorder passed
CC00500000007503619/10/2022Sahebrao Baban Sable vs Pankaj Prakash Yeolaorder passed
CC00500000011705530/04/2022Nilesh Kumar Soni vs Pankaj Prakash Yeolaorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered05 Dec 2019Delay in obtaining Completion Certificate

Location, Land & Connectivity

Located at -, -, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by ORABELLE PHASE II BUILDING C AND D, to the south by PCMC GARDEN, to the east by SURVEY NUMBER 138 and to the west by SURVEY NUMBER 121. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park7 km
Baner–Balewadi belt11 km
Pune Junction / city centre19 km
Pune Int'l Airport (Lohegaon)20 km
Kharadi / EON IT Park23 km
Magarpatta / Hadapsar IT24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pankaj Prakash Yeola is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Pankaj Prakash Yeola project & its RERA track record →

Other flagged projects by Pankaj Prakash Yeola

Pankaj Prakash Yeola
Past its declared completion datePune
Pankaj Prakash Yeola
Registration suspendedPune

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Bhoomi Orabelle Phase II
declared completion Dec 2020 · Pankaj Prakash Yeola
Bhoomi Orion
declared completion Dec 2019 · Bhoomi Developers
Bhosale Empire
possession by Dec 2026 · Morus Developers
Bhosale Empire
possession by Dec 2026 · Bhakti Developers
Bhosale Galaxy
possession by Jun 2028 · Bhosale Properties LLP
Bhosale Icon
possession by Sep 2027 · Bhosale Housing LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.