MahaRERA Property Intelligence · Pune
P52100005682 · RAVET · promoter Dolphin Buildcon
| MahaRERA registration | P52100005682 |
| Registered on | 11 Aug 2017 |
| Promoter-declared completion | 29 Dec 2022 |
| Current status | Certificate Signed |
| Against today | about 43 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Dolphin Buildcon is the promoter of record on 18 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| CASA GRANDE B WING | 1 | G+20 | 31 Dec 2020 |
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| C J J D And Jmfc Pimpri Chinchwad | RCS 0000089 | 2010 | Issues |
| C J S D Pune | 474 /2016 | 2016 | Exh Five Partly Allowed Against Silver Star Group |
| District Judge Pune | 164/2015 | 2015 | Notice Unready |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 29 Dec 2022 | 29 Jun 2022 | DUE TO SCARCITY OF LABOUR,MATERIAL ,TRANSPORT DURING LOCKDOWN 1 AND 2,THE ENTIRE WORK OF THE SITE CAME TO STAND STILL. We are applying for first time extension. Hence in our ca |
Located at RAVET, RAVET BRT ROAD, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by PARTLY REMAINING AREA OF SR NO 89 BY AND 189 BY 3, to the south by BRT ROAD, to the east by REMAINING AREA OF SURVEY NO 89 BY 1RAVET and to the west by SURVEY NO 88. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 7 km |
| Baner–Balewadi belt | 11 km |
| Pune Junction / city centre | 19 km |
| Pune Int'l Airport (Lohegaon) | 20 km |
| Kharadi / EON IT Park | 24 km |
| Magarpatta / Hadapsar IT | 25 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in CASA GRANDE B WING?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Dolphin Buildcon is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026