MahaRERA Property Intelligence · Pune

Citywoods Pine

P52100011908 · promoter Spire Associates

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52100011908
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Spire Associates is the promoter of record on 18 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
C Pine1G+17-

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000001092420/02/2018Ghevarchand Ganeshmal Dhumavat vs Spire Associates, Jayantilal Tarachand Oswalorder passed
CC00500000037099129/05/2024GHEVARCHAND DHUMAVAT vs M/S SPIRE ASSOCIATESorder passed
CC1250088113/03/2025GHEVARCHAND DHUMAVAT vs Spire Associatesorder passed
CC1250158914/05/2025Hitesh Satra vs Spire Associatesorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202419 Sep 2023THE PROJECT WAS ON GOING PROJECT WITH PENDING LITIGATIONS SINCE 10 YRS.NOW LITIGATIONS ARE SETTLED BUT WE NOT ABLE TO SELL FLATS AND WE HAVE TO INVEST MONEY FROM OTHER SOURCES.WE H
31 Dec 202431 Dec 2024We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52100011908 up to 31/12/2024. As prescribed under circular no 07/2019 dated 8 Feb 2019, the con

Location, Land & Connectivity

Located at Pune City, Pune, 411037. Per the filed land record, the plot is bounded to the north by Road, to the south by Road, to the east by Road and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre4 km
Magarpatta / Hadapsar IT6 km
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)11 km
Baner–Balewadi belt13 km
Hinjewadi Rajiv Gandhi IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bibwewadi

Celia Phase 2
Not filing quarterly progress reports · possession by Jul 2026 · Enerrgia Developers
Ravindu
possession by Jul 2026 · Shubh Ventures
Siddhachal - A1
possession by Jul 2026 · Viraj Properties (now Known As Viraj Pro
Indian Bank Staff CO-Operative Housing Society LTD
possession by Aug 2026 · Raichandani Constructions Private Limite
Siddhi -Siddhachal
possession by Aug 2026 · Bhairav Promoters Unit Number 1
Osian Navkar
possession by Sep 2026 · Osian Realty

Major developers building in Bibwewadi

Other RERA-registered projects in Pune

Civcon Residency
declared completion Aug 2025 · Archway Properties
Classic Amrut
possession by Oct 2026 · Classic Infra
Classic Exotica B
declared completion Dec 2022 · Classic Developers
Classic Gloria Building A
declared completion Dec 2024 · Classic Properties
Classic Gloria Building B
declared completion Mar 2026 · Classic Properties
Classic Icon
declared completion Sep 2021 · Shamrao Sukhadeo Patil

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026