Pune/Project record

MahaRERA · the public record

EVERNEST PHASE 2

URAVADE · NKG PROPERTIES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100055476

Delivery and registration

When is the project declared for completion?

EVERNEST PHASE 2 is registered with MahaRERA as P52100055476 and the promoter has declared completion for 31 Mar 2026.

31 Mar 2026

declared completion

6months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100055476
Registered on02 Apr 2024
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 6 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EVERNEST PHASE 2 record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In EVERNEST PHASE 2, 4 of 10 plots filed with MahaRERA are recorded as sold or booked, about 40%, and 6 remain available.

40%sold

4 of 10 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for EVERNEST PHASE 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at URAVADE, Lavasa Bhukum Link Road, Pune City, Pune, 412115. Per the filed land record, the plot is bounded to the north by by land bearing gat no 441, to the south by by land bearing gat no 805, to the east by By land bearing Gat no 449 and to the west by By land bearing gat no 447. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhugaon

Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Asmi Pride
possession by Dec 2026 · M/S Icon Developers
Madhuban
possession by Dec 2026 · NG Rathi Estate
Plumeria, Viva, Pirangut
Deregistered by MahaRERA · possession by Dec 2026 · K Raheja Corp Real Estate Private Limite

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Evernest Shivshrushti
possession by Dec 2026 · Evernest Perfectinfra LLP
Everra Phase 1
possession by Dec 2031 · Honcho Properties Private Limited
Eves Garden Phase VI
declared completion Jun 2024 · Sancheti Properties
Evexia Exotica
possession by Dec 2030 · Sankalp Infra
Evexia Imperia
declared completion Jun 2026 · Evexia Buildcon LLP
Evolet Tiara
possession by Dec 2026 · M/S Evolet Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026