MahaRERA Property Intelligence · Pune
P52100001285 · Koregaon mul · promoter Gagan Horizon Ventures
| MahaRERA registration | P52100001285 |
| Registered on | 27 Jul 2017 |
| Promoter-declared completion | 31 Dec 2019 |
| Current status | Certificate Signed |
| Against today | about 79 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Gagan Horizon Ventures is the promoter of record on 40 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| BUILDING A1 | 1 | G+8 | 31 Dec 2018 |
| BUILDING A2 | 1 | G+8 | 31 Dec 2018 |
| BUILDING A3 | 1 | G+8 | 31 Dec 2018 |
| BUILDING A4 | 1 | G+8 | 31 Dec 2018 |
| BUILDING A5 | 1 | G+8 | 31 Dec 2018 |
20 complaints are on the MahaRERA record for this project, with orders passed in 20. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000010933 | 25/01/2018 | Jyoti Vidyadhar Pinjarkar vs Gagan Horizone Ventures through its Partner Sushil Agrawal | order passed |
| CC005000000000091 | 05/09/2017 | SUNIL NATHURAM UTTEKAR vs GAGAN HORIZON VENTURES | order passed |
| CC005000000011128 | 15/03/2018 | PALLAVI YOGESH GAVATE vs M/S GAGAN HORIZON VENTURES | order passed |
| CC005000000022028 | 06/10/2018 | Sushant Suhas Gaikwad and Manasi Sushant Gaikwad vs Gagan Horizon Ventures | order passed |
| CC005000000022077 | 09/10/2018 | PRAKASH PATEL vs NILESH LADDAD | order passed |
| CC005000000022106 | 04/10/2018 | VINOD PRAKASH DEOKAR vs GAGAN HORIZON VENTURE | order passed |
| CC005000000022107 | 04/10/2018 | Yojana Vinod Deokar vs Gagan Horizon Ventures | order passed |
| CC005000000022134 | 15/10/2018 | Sandesh Janardhan Kale vs Gagan Horizon Ventures | order passed |
| CC005000000022760 | 08/03/2019 | hemant Martandrao kulkarni and 1 other vs Gagan Horizon Ventures and ors | order passed |
| CC005000000022990 | 06/05/2019 | NITIN SADASHIV TEKAWADE & SEEMA NITIN TEKAWADE vs GAGAN HORIZON VENTURES | order passed |
| CC005000000022960 | 27/04/2019 | Ketan Dilip Shah vs Gagan Horizon Venture | order passed |
| CC005000000023097 | 05/06/2019 | JAYASHRI RAJANIKANT SIKACHI vs GAGAN HORIZON VENTRES | order passed |
| CC005000000023215 | 21/07/2019 | Benjamin Samul Gadkar and Saurabh Benjamin Gadkar vs Gagan Horizon Ventures through its partners Pramod Mohanlal Bafna and Nilesh Ishwar Ladd | order passed |
| CC005000000023407 | 08/09/2019 | Mrs.Kalpana Ankush Pomane vs Gagan Horizon Ventures thorugh its authorized person | order passed |
| CC005000000033591 | 24/11/2019 | Ajinkya Vijay Ghare vs Gagan Horizon Ventures | order passed |
| CC005000000043662 | 19/11/2019 | NASIR IBRAHIM PENDHARI vs GAGAN HORIZON VENTURES | order passed |
| CC005000000064903 | 08/04/2021 | Kapil Tukaram Nadgeri vs M/S Gahan Horizon Venture partner Mr. Sushil Ghanshyam Agarwal & Mr. Nilesh Ishwar Laddad | order passed |
| CC005000000085293 | 02/03/2021 | NAZIMA ISMAIL PATEL vs GAGAN HORIZON VENTURES THROUGH ITS AUTHORIZED SIGNATORY | order passed |
| CC005000000085385 | 25/03/2021 | Mr Kalyan Dattatray Shinde vs Mrs Varsha Kalyan Shinde | order passed |
| CC005000000085483 | 22/04/2021 | Mr Sunil Pralhad Wavare vs GAGAN HORIZON VENTURES THROUGH ITS AUTHORIZED SIGNATORY | order passed |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Dec 2019 | 31 Dec 2019 | The project “Gagan Akanksha” situated at Gat no 524, Koregaon Mul, Taluka Haveli, District Pune has been registered with Hon’ble RERA authority under registration no. P52100001285 |
Located at Koregaon mul, Koregaon Mul, Pune City, Pune, 411202. Per the filed land record, the plot is bounded to the north by PROPOESD 24M DP ROAD, to the south by GAT NO 526, to the east by GAT NO 525 and to the west by GAT NO 523. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Kharadi / EON IT Park | 19 km |
| Magarpatta / Hadapsar IT | 19 km |
| Pune Int'l Airport (Lohegaon) | 22 km |
| Pune Junction / city centre | 25 km |
| Baner–Balewadi belt | 36 km |
| Hinjewadi Rajiv Gandhi IT Park | 40 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in GAGAN AKANKSHA PHASE 1?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026