Pune/Project record

MahaRERA · the public record

Gandharv Nagari A6

Gandharva Nagari Moshi · Vinayak Pandharinath Bhongale

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

2units filed as unsoldInventory · 18 September 2026
30 Jun 2026declared completionMahaRERA registration · read 12 Jul 2026
13registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100047726

Delivery and registration

When is the project declared for completion?

Gandharv Nagari A6 is registered with MahaRERA as P52100047726 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

3months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100047726
Registered on21 Nov 2022
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gandharv Nagari A6 record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vinayak Pandharinath Bhongale is the promoter of record on 36 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

36projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Gandharv Nagari A6, ₹2.46 Cr of a declared ₹2.46 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.

100.0%

₹2.46 Cr

of ₹2.46 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Gandharv Nagari A6, 11 of 13 homes filed with MahaRERA are recorded as sold or booked (9 with registered agreements and 2 booked), about 85%, and 2 remain available.

85%sold

11 of 13 homes

₹4.32 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹2.53 Cr (about 59%) is recorded as collected and ₹1.79 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 11 registered agreements, the effective carpet rate is ₹9,111/sqft, with eight in ten falling between ₹8,172 and ₹10,242 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Ground/Floor 01157 sqft (14.55 sqm)₹9.65 Lakh
Ground/Floor 03155 sqft (14.4 sqm)₹9.55 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 11 homes carry one, and 2 of the 13 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Gandharv Nagari A6, 0 of the 2 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 2 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 13 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Gandharv Nagari A61G+413-

Unit mix on the filing: 10 residential and 3 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Oct 2025Due to non-availability of rock in Land excavation for foundation structural design required changed and hence delay is caused to start the construction of building and hence proje
30 Oct 202530 Jun 2026since 5th July 2025 due to heavy Rain, labour camp was disturbed and was shifted at remote place. That cement bricks & other concrete mixture equipment’s could not be brought to si

Location, Land & Connectivity

Located at Gandharva Nagari Moshi, Pune nashik highway, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by 7 5 Mtr Road, to the south by Internal Road and remaining land of Gat no 452 1 1, to the east by 6 Mtr Road and to the west by Remaining Land of Gat no 452 1 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)10 km
Baner–Balewadi belt13 km
Hinjewadi Rajiv Gandhi IT Park14 km
Pune Junction / city centre14 km
Kharadi / EON IT Park14 km
Magarpatta / Hadapsar IT17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vinayak Pandharinath Bhongale is the promoter on 13 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Vinayak Pandharinath Bhongale project & its RERA track record →

Other flagged projects by Vinayak Pandharinath Bhongale

Vinayak Pandharinath Bhongale
FlaggedPune
Vinayak Pandharinath Bhongale
FlaggedPune
Vinayak Pandharinath Bhongale
FlaggedPune
Vinayak Pandharinath Bhongale
FlaggedPune
Vinayak Pandharinath Bhongale
FlaggedPune

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Gandharv Nagari Building A3 Wing A, B
declared completion Sep 2026 · Vinayak Pandharinath Bhongale
Gandharva Nagari
possession by May 2031 · Manasara Vaastu Private Limited
Gandharva Nagari Phase II, Project II, G-12
declared completion Dec 2020 · Vinayak Pandharinath Bhongale
Gandhi Empire 3X
possession by Dec 2031 · Navantilal Uttamchand Gandhi
Gandle Heights
declared completion Jun 2025 · M/s. Vaibhavlaxmi Developers
Ganesh Bella Montana
declared completion Dec 2025 · Veddant Shelters

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026