MahaRERA Property Intelligence · Pune
P52100026055 · TATHAWDE · promoter Shri Siddhivinayak Developers
| MahaRERA registration | P52100026055 |
| Registered on | 12 Aug 2020 |
| Promoter-declared completion | 30 Jun 2027 |
| Current status | Certificate Signed |
| Against today | 11 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~39.6% of the estimated project cost incurred as of the last certificate (₹21.86 Cr spent against a ₹55.15 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. With only ~11 months to the declared date and ~39.6% of the cost incurred, ask the promoter how the balance gets built in the time left.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 96 homes filed with MahaRERA, 90 are sold/booked and 6 remain available (~94% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹53.32 Cr in agreement value so far. Of that, ₹17.61 Cr (~33%) is already collected, ₹35.70 Cr receivable — a read on how far along these sales really are. Note: the project registers 206 homes in total, but this sold/unsold inventory filing covers only 96 of them — the other 110 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 90 registered agreements, the effective carpet rate is ₹7,818/sqft (typical range ₹6,909–₹9,044) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | 103 | 790 sqft (73.35 sqm) | ₹56.75 Lakh |
| Floor 4 | 404 | 790 sqft (73.35 sqm) | ₹56.75 Lakh |
| Floor 5 | 502 | 650 sqft (60.41 sqm) | ₹49.15 Lakh |
| Floor 7 | 703 | 779 sqft (72.35 sqm) | ₹58.77 Lakh |
| Floor 7 | 705 | 605 sqft (56.22 sqm) | ₹4.56 Cr |
| Floor 9 | 905 | 605 sqft (56.22 sqm) | ₹45.67 Lakh |
⚠ The inventory filing also declares: 85 owner/investor-held and 25 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 206 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| D | 1 | G+13 | 103 | 30 Jun 2025 |
| E | 1 | G+13 | 103 | 30 Jun 2025 |
Unit mix on the filing: 206 residential.
23 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12500706 | 28/02/2025 | Devendra Yashwant Palav vs Anuj Goel | pending / no order on file |
| CC12500705 | 28/02/2025 | BHAGAWAN VISHWANATH SHRIRAME vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12500655 | 24/02/2025 | Shrushti Prashant Deshmukh vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12500717 | 01/03/2025 | Sunil Wamanrao Kadam vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12500701 | 28/02/2025 | Lalit Ravindra Amrutkar vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12500704 | 28/02/2025 | Abhishek CHANDRAKANT Yadav vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12501031 | 27/03/2025 | Mayur Lalchand Jiwatramani vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC12501127 | 04/04/2025 | sangeeta Sameer Bhole vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12502199 | 02/07/2025 | SONAL SAGAR LAKADE vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12503474 | 29/09/2025 | Neha Ganesh Bhole vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12503475 | 29/09/2025 | mayur umesh phadke vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12503500 | 30/09/2025 | Vaibhav ganesh Bhole vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
| CC12604459 | 17/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Mr Abhishek Chandrakant Yadav | pending / no order on file |
| CC12604460 | 17/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Shrusti Prashant Deshmukh | pending / no order on file |
| CC12604461 | 17/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Neha Ganesh Bhole | pending / no order on file |
| CC12604462 | 17/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Lalit Ravindra Amrutkar | pending / no order on file |
| CC12604472 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Sunil Wamanrao Kadam | pending / no order on file |
| CC12604475 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Vaibhav Ganesh Bhole | pending / no order on file |
| CC12604481 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Mayur Umesh Phadke | pending / no order on file |
| CC12604483 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Bhagwan Vishwanath Shrirame | pending / no order on file |
| CC12604486 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Devendra yashwant Palav | pending / no order on file |
| CC12604489 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Sonal Sagar Lakade | pending / no order on file |
| CC12604493 | 18/07/2026 | SHRI SIDDHIVINAYAK DEVELOPERS vs Sangeeta Sameer Bhole | pending / no order on file |
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2025 | 29 Jun 2026 | Non-availability of labor and other resources. |
| 30 Jun 2025 | 30 Jun 2027 | The project timeline has been impact as promoter was required to replace construction contractor engaged for Building D & E resulting in disruption of the construction schedule and |
Located at TATHAWDE, AMBER STREET, Pune City, Pune, 411033. Per the filed land record, the plot is bounded to the north by S NO 60 PART, to the south by S NO 59 PART, to the east by S NO 60 PART and to the west by S NO 59 AND 60 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 3 km |
| Baner–Balewadi belt | 7 km |
| Pune Junction / city centre | 16 km |
| Pune Int'l Airport (Lohegaon) | 18 km |
| Kharadi / EON IT Park | 21 km |
| Magarpatta / Hadapsar IT | 21 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in GANGA AMBER PH II?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Shri Siddhivinayak Developers is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026