Pune/Project record

MahaRERA · the public record

GEETA VALLEY

Tathwade · White Water Infratech Pvt. Ltd

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100030193

Delivery and registration

When is the project declared for completion?

GEETA VALLEY is registered with MahaRERA as P52100030193 and the promoter has declared completion for 30 Apr 2024.

30 Apr 2024

declared completion

29months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100030193
Registered on05 Aug 2021
Promoter-declared completion30 Apr 2024
Current statusCertificate Signed
Against todayabout 29 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GEETA VALLEY record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

White Water Infratech is the promoter of record on 183 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

183projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GEETA VALLEY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
GEETA VALLEY1G+631 May 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2024We have already completed 90% of the project. However, due to some financial issues, the construction pace got halted and thus we seek extension. We shall complete the project with

Location, Land & Connectivity

Located at Tathwade, Tathwade, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by By Road, to the south by By Land of Mr Pawar, to the east by By Land of Mr Pawar and to the west by By Land of Mr Bhosale. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Geetali Co Op Housing Society Ltd
possession by May 2029 · Exito Infrastructure Pvt Ltd
Geetanjali A Apartment
possession by Jun 2027 · Sarthak Housing Development Corporation
Geetanjali Namana Apartment
declared completion Jun 2023 · D & T Properties
Geetmala Green City
possession by Dec 2028 · Saptashrungi Developers
Geetvan
possession by Mar 2029 · M/S Shilp Properties
Gen1
possession by Dec 2026 · Bishnoi Kalamkar Constructions LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026