GRAZIA

P52100052712 · KOTHRUD · promoter Sbm Space Realty

Certificate SignedDue 30 Jun 2026

Delivery & Registration

MahaRERA registrationP52100052712
Registered on22 Sep 2023
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹7.55 Cr spent against a ₹7.55 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 18 homes filed with MahaRERA, 16 are sold/booked and 2 remain available (~89% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹19.71 Cr in agreement value so far. Of that, ₹14.27 Cr (~72%) is already collected, ₹5.44 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 16 registered agreements, the effective carpet rate is ₹14,985/sqft (typical range ₹10,820–₹16,261) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 3302929 sqft (86.34 sqm)₹72.51 Lakh
Floor 6602929 sqft (86.34 sqm)₹72.51 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 18 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Grazia1G+518-

Unit mix on the filing: 18 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202530 Jun 2026The project was delayed due to a continuous shortage of both construction materials and labour. Essential materials such as cement, steel, sand, and other supplies were not receive

Location, Land & Connectivity

Located at KOTHRUD, LEFT BHUSARI COLONY, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by BY 30 FEET ROAD, to the south by BY PLOT NO 31, to the east by BY PLOT NO 28 and to the west by BY 40 FEET COLONY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt7 km
Pune Junction / city centre8 km
Hinjewadi Rajiv Gandhi IT Park12 km
Magarpatta / Hadapsar IT13 km
Pune Int'l Airport (Lohegaon)15 km
Kharadi / EON IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kothrud

Umed
possession by Jul 2026 · Runwal Realtors Pvt Ltd
Chandra Apartment
possession by Aug 2026 · Deshpande Landmark Private Limited
Keshar
possession by Aug 2026 · Badhekar Properties
Tungabhadra CO OP HSG SOC
possession by Aug 2026 · Not Available
Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates

Major developers building in Kothrud

Other RERA-registered projects in Pune

Green Alley Phase - I
possession by Dec 2026 · Ajinkya Sanjay Tapkir
Green Alley Phase - II
possession by Dec 2026 · Aryan Developers
Green Aura-1
possession by Mar 2027 · Bhagyashree Yuvraj Kakade
Green Aura 3
possession by Mar 2027 · Pallavi Mohan Naik
Green Aura 4
possession by Mar 2027 · Dimple Ganpat Sharma
Green Avenue
declared completion Jan 2021 · Green Concept Builders & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026