Pune/Project record

MahaRERA · the public record

GULMOHAR RESIDENCY

CHAKAN · ISHWARI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Jun 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Jun 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014688

Delivery and registration

When is the project declared for completion?

GULMOHAR RESIDENCY is registered with MahaRERA as P52100014688 and the promoter has declared completion for 29 Jun 2020.

29 Jun 2020

declared completion

75months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014688
Registered on26 Dec 2017
Promoter-declared completion29 Jun 2020
Current statusCertificate Signed
Against todayabout 75 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GULMOHAR RESIDENCY record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GULMOHAR RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Gulmohar Residency1G+530 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020We are in process of revision of sanctioned plan to accommodate balance FSI. We have applied to PMRDA Pune for revision of plan. The copy of acknowledgement of submission of revise

Location, Land & Connectivity

Located at CHAKAN, GAT NO 480 P, Khed, Pune, 410501. Per the filed land record, the plot is bounded to the north by 18451375, to the south by 6M WIDE ROAD, to the east by 73510739 and to the west by GAT NO 2429. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~99 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park99 km
Baner–Balewadi belt105 km
Pune Junction / city centre115 km
Pune Int'l Airport (Lohegaon)115 km
Kharadi / EON IT Park119 km
Magarpatta / Hadapsar IT120 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Gulmohar Residency
declared completion Jun 2022 · Avitejclassic
Gulmohar Residency
declared completion Dec 2025 · Srushti Developers
Gulmohar Skypark
possession by Jun 2027 · LEO Construction
Gulmohar Society
possession by Dec 2027 · Nitin Sitaram Kulkarni
Gulmohar Villas - A
declared completion Dec 2024 · Natraj Shamrao Satav
Gulmohar Villas - C
declared completion Dec 2024 · Nalini Chowdary Gogineni

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026