P52100034817 · URSE · promoter Balasaheb Chaburao Dhamankar

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP52100034817
Registered on28 Apr 2022
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Balasaheb Chaburao Dhamankar is the promoter of record on 64 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at URSE, SURVEY NO 224, Mawal, Pune, 410506. Per the filed land record, the plot is bounded to the north by SURVEY NO 224 PART AREA OF RAMDAS DHAMANKAR, to the south by ROAD, to the east by SURVEY NO 224 PART and to the west by ROAD AND SURVEY NO 256. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~18 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park18 km
Baner–Balewadi belt23 km
Pune Junction / city centre33 km
Pune Int'l Airport (Lohegaon)34 km
Kharadi / EON IT Park37 km
Magarpatta / Hadapsar IT38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Talegaon Dabhade

One Lonvala
possession by Aug 2026 · Holy Valley Lifescapes Private Limited
Vaarivana Phase D - 2A
possession by Oct 2026 · Sanjivani Integrated Township LLP
Rohan Anand Phase II
possession by Dec 2026 · Rohan Builders & Developers Private
Abhimaan Homes Phase 3
possession by Dec 2026 · Rising Propcon LLP
Aditya Vardhan Heights
possession by Dec 2026 · Shree Ganesh Developers
City Plaza
Past its declared completion date · possession by Dec 2026 · Shreenathji Construction LLP

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Ibz Hinjewadi
possession by Dec 2029 · Rising High Ventures
Ichhapurti Residency
declared completion Aug 2019 · Shreyash Engineers AND Developers
Icon 51
declared completion Jun 2024 · S M Square Constro LLP
Icon Auria
possession by Dec 2027 · Icon Properties
Icon Avanza
possession by Dec 2028 · Icon Ventures
Icon Business Spaces
declared completion Aug 2025 · Icon Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026