Pune/Project record

MahaRERA · the public record

INFINITY EVANA

Punawale · TULIP INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

317units filed as unsoldInventory · 20 September 2026
30 Jun 2029declared completionMahaRERA registration · read 12 Jul 2026
642registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100078470

Delivery and registration

When is the project declared for completion?

INFINITY EVANA is registered with MahaRERA as P52100078470 and the promoter has declared completion for 30 Jun 2029.

30 Jun 2029

declared completion

33months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100078470
Registered on12 Dec 2024
Promoter-declared completion30 Jun 2029
Current statusCertificate Signed
Against today33 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INFINITY EVANA record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tulip Infratech is the promoter of record on 22 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In INFINITY EVANA, ₹5.13 Cr of a declared ₹92.05 Cr estimated project cost is reported as incurred, about 5.6%, as at the last certified filing with MahaRERA.

5.6%

₹5.13 Cr

of ₹92.05 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In INFINITY EVANA, 0 of 540 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 540 remain available.

0%sold

0 of 540 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 642 homes in total, while this sold/unsold inventory filing covers 540 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 102 not for sale.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 219 homes carry one, and 317 of the 643 are recorded unsold. Since we started watching this ledger, 219 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
D-8684 sqftRs 9,823 a sq ft typical, over Rs 7,968 to Rs 11,12184 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In INFINITY EVANA, 167 of the 317 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 316 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+49 and 642 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A Wing1G+49204-
C Wing1G+33137-
D Wing 1G+32143-
B Wing1G+49112-
E Wing MHADA1G+2046-

Unit mix on the filing: 506 residential and 136 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2029The project was originally registered with a proposed date of completion 31.12.2028. We submitted our application for environmental clearance on 05.02.2025, and same is withdrawal

Location, Land & Connectivity

Located at Punawale, Malwadi, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by Pavana River , to the south by Road , to the east by 12 Mtr Road & out of Survey No. 43 and to the west by Survey No. 43/8, 43/1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park5 km
Baner–Balewadi belt10 km
Pune Junction / city centre19 km
Pune Int'l Airport (Lohegaon)21 km
Kharadi / EON IT Park24 km
Magarpatta / Hadapsar IT25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tulip Infra is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Tulip Infra project & its RERA track record →

Other flagged projects by Tulip Infra

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Infinity Heights
possession by Dec 2026 · Khond Patil Developers
Infinity Planet A Wing
possession by Jun 2027 · Tulip Properties
Infinity Planet E Wing
declared completion May 2026 · Tulip Properties
Infinity Pride
declared completion Dec 2023 · Snehmangal Tulip Developers
Infinity Solaria
possession by Dec 2029 · Tulip Realty
Infinity Spaces
possession by Dec 2026 · Infinity Infracorp

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.