Pune/Project record

MahaRERA · the public record

KESHAV KUNJ

WADAGAON MAWAL · GRAYSTONE REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100081012

Delivery and registration

When is the project declared for completion?

KESHAV KUNJ is registered with MahaRERA as P52100081012 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100081012
Registered on13 Oct 2025
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KESHAV KUNJ record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KESHAV KUNJ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
WING A1G+6-
WING B1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at WADAGAON MAWAL, MHASALKAR WASTI, Mawal, Pune, 412106. Per the filed land record, the plot is bounded to the north by 9 MTR ROAD, to the south by 6 MTR ROAD, to the east by PLOT NO 24 and to the west by AMENITY SPACE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
possession by Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
possession by Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Surya Heights
possession by Dec 2026 · SSB Developer

Major developers building in Vadgaon Maval

Other RERA-registered projects in Pune

Keshavbaag
declared completion Dec 2022 · Shlok Enterprises
Keshavyog Residency
possession by Dec 2026 · Siddhivinayak Builders
Ketan Heights Chsl
possession by Dec 2026 · Kotibhaskar Infrastructures &develop
Ketan Heights Wing / Building No A
possession by Dec 2026 · Ketandevelopers
Ketki
possession by Jul 2027 · NEW Vision Ventures
Kewal Kunj
possession by Mar 2028 · Bora Excellency Developers Unit 1

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026