Pune/Project record

MahaRERA · the public record

Dreams Ayana P1 P2 P3 Q1 wings

MAWAL · Kohinoor Dreams Associates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100006130

Delivery and registration

When is the project declared for completion?

Dreams Ayana P1 P2 P3 Q1 wings is registered with MahaRERA as P52100006130 and the promoter has declared completion for 31 Jul 2019.

31 Jul 2019

declared completion

86months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100006130
Registered on14 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 86 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Dreams Ayana P1 P2 P3 Q1 wings record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kohinoor Dreams Associates is the promoter of record on 40 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

40projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Dreams Ayana P1 P2 P3 Q1 wings in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
P11G+531 Jul 2019
P21G+531 Jul 2019
P31G+531 Jul 2019
Q11G+531 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Jr Div Vadgaon Maval5652012Say On Exhibit

Location, Land & Connectivity

Located at MAWAL, PUNE, Pune City, Pune, 412106. Per the filed land record, the plot is bounded to the north by Wing P 4 Open Space 02, to the south by G No 682, to the east by Proposed ph 2 and to the west by G No 682. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park23 km
Baner–Balewadi belt28 km
Pune Junction / city centre38 km
Pune Int'l Airport (Lohegaon)39 km
Kharadi / EON IT Park42 km
Magarpatta / Hadapsar IT43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
possession by Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
possession by Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Surya Heights
possession by Dec 2026 · SSB Developer

Major developers building in Vadgaon Maval

Other RERA-registered projects in Pune

Dreams Carnival Platinum
possession by Dec 2027 · SAM Developers
Dreams Icon
possession by Apr 2027 · Umiya Realty
Dreams Lynnea A B Wings
declared completion Sep 2020 · Dreams Construction Pvt. Ltd.
Dreams Onella B Wing
declared completion May 2022 · Dreams Arc Developers
Dreams Rachana C D Wings
declared completion Jun 2023 · Dreams Construction Pvt. Ltd.
Dreams Rakshak
possession by Dec 2027 · New Dream Landmark AOP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026