Dreams Lynnea A B wings

Pune · Dreams Construction ( Pune) Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100000237

Delivery and registration

When is the project declared for completion?

Dreams Lynnea A B wings is registered with MahaRERA as P52100000237 and the promoter has declared completion for 30 Sep 2020.

30 Sep 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100000237
Registered on10 Jul 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Dreams Lynnea A B wings record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dreams Construction Pune) is the promoter of record on 31 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Dreams Lynnea A B wings in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
A wing1G+1331 Mar 2019
B wing1G+1331 Mar 2019
Club House1G+1-

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for Dreams Lynnea A B wings, with orders passed in 10 of them.

10complaints

10with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001170403/07/2018AMIT HARIBHAU BHAGWAT vs Dreams Lynnea Through its Signatory Dream Construction pune Pvt.Ltdorder passed
CC00500000001154420/05/2018Prasad Raghunath Khandare vs Ramesh Ghisulal Mehtaorder passed
CC00500000002287112/04/2019GULSHAN KUMAR vs Dreams Construction (PUne) P Limitedorder passed
CC00500000003353214/10/2019Indu Jha vs Dreams Construction (Pune) Pvt. Ltd through it's Director Mr. Ramesh Ghisulal Mehtaorder passed
CC00500000002310414/06/2019DHARAMDAS TRILOKCHANDANI vs DREAMS CONSTRUCTION (PUNE) PVT. LTDorder passed
CC00500000003346129/09/2019Rakesh Kumar Seal vs Umesh Ambardekarorder passed
CC00500000005388604/01/2020Kaavya Trilokchandani vs Ramesh Ghisulal Mehtaorder passed
CC00500000005403717/02/2020Haresh Prakshlal Kundal vs Dreams Constructions (Pune) Pvt Ltd Companyorder passed
CC00500000005403517/02/2020Lalit H Nihalani vs Dreams Construction (Pune) Pvt Ltd companyorder passed
CC00500000005403414/02/2020Shivkumar Chanchaldas Trilokchandani vs Dreams Constructions (Pune) Pvt. Ltd. Companyorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2020Due to duel impact of GST & Demonetisation the clash flow was badly hampered...

Location, Land & Connectivity

Located at Pune City, Pune, 412207. Per the filed land record, the plot is bounded to the north by 2nd phase C wing, to the south by 954 955 956, to the east by 884 and to the west by 895. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Kharadi / EON IT Park6 km
Pune Int'l Airport (Lohegaon)7 km
Magarpatta / Hadapsar IT9 km
Pune Junction / city centre13 km
Baner–Balewadi belt22 km
Hinjewadi Rajiv Gandhi IT Park26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
possession by Nov 2026 · Defence Colony Pune

Major developers building in Wagholi

Other RERA-registered projects in Pune

Dreams Onella B Wing
declared completion May 2022 · Dreams Arc Developers
Dreams Rachana C D Wings
declared completion Jun 2023 · Dreams Construction Pvt. Ltd.
Dreams Rakshak
possession by Dec 2027 · New Dream Landmark AOP
Dreams Riviera
declared completion Dec 2024 · Ashtavinayak Infra
Dreams Riviera A Wing
possession by Mar 2028 · Ashtavinayak Infra
Dreams Wisteria
declared completion Jul 2025 · Dattatray Sambhajirao Dhangekar

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026