Pune/Project record

MahaRERA · the public record

La Montana Phase III

MIDC Gate Chowk , Near Sheetal Hotel, Talegaon, · Tata Value Homes Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100000145

Delivery and registration

When is the project declared for completion?

La Montana Phase III is registered with MahaRERA as P52100000145 and the promoter has declared completion for 30 Mar 2021.

30 Mar 2021

declared completion

66months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100000145
Registered on05 Jul 2017
Promoter-declared completion30 Mar 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for La Montana Phase III record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tata Housing is the promoter of record on 25 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

25projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for La Montana Phase III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
La Montana Sierra1G+1530 Sep 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for La Montana Phase III, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001054209/11/2017Ramesh M. Tavhare vs Tata Value Homes Ltd.order passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Sub Divisional Officer Maval151/20152015Tvhl Had Received A Notice From The Tehsildar Pune For Payment Of Royalty Towards Excavation Of Rs O
Sub Divisional Officer Maval190/20162016The Adjacent Land Owner Mr Sitaram Dhore Wants A Right Of Access Through Tvhl Project Property Mr Si
Before The Ld Sole Arbitrator Mr Shailesh Shah Sr Adv-----2014The Matter Is Kept For Inspection Of The Documents And Exchange Of Draft Issues By Both The Parties
High Court BombayWPST/36660/20182018Pre Admission Date Not Yet Assigned

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2020We are developing the project 'La Montana - Phase III' and have received the Occupancy Certificate dated on 24 June 2019. The promoter is in process of handing over the residential

Location, Land & Connectivity

Located at MIDC Gate Chowk , Near Sheetal Hotel, Talegaon, , Mumbai - Pune Highway, Mumbai City, Mumbai City, 412106. Per the filed land record, the plot is bounded to the north by Proposed R P Road , to the south by Survey No 126 3, to the east by Survey No 127 and to the west by Survey No 126 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park18 km
Baner–Balewadi belt23 km
Pune Junction / city centre33 km
Pune Int'l Airport (Lohegaon)33 km
Kharadi / EON IT Park37 km
Magarpatta / Hadapsar IT38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tata Value Homes Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Tata Value Homes Limited project & its RERA track record →

Other flagged projects by Tata Value Homes Limited

Tata Value Homes Limited
FlaggedPune

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
possession by Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
possession by Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Surya Heights
possession by Dec 2026 · SSB Developer

Major developers building in Vadgaon Maval

Other RERA-registered projects in Pune

La Montana Phase IV
declared completion Jan 2026 · Tata Value Homes Limited
LA Royale - A Building
declared completion Dec 2022 · Devi Shakti Realty LLP
LA Royale - B Building
declared completion Dec 2023 · Devi Shakti Realty LLP
LA Royale - C Building
declared completion Dec 2022 · Devi Shakti Realty LLP
La Royale - Phase I
declared completion Jan 2021 · Devi Homes
LA Vista
declared completion Apr 2026 · Darshanraj Reality

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026