MahaRERA Property Intelligence · Pune

LA ROYALE - B BUILDING

P52100012483 · promoter Devi Shakti Realty

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP52100012483
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Devi Shakti Realty is the promoter of record on 129 projects, of which 19 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
BUILDING B1G+11-

Complaints & Orders

8 complaints are on the MahaRERA record for this project, with orders passed in 8. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000001102022/07/2019Shailesh Mahadev Parkhe vs Shree Devi Land Developers LLPorder passed
CC00500000001119522/09/2018Rajiv Krishna Kadam vs Devi Shekti Realty LLP - Property LA Royaleorder passed
CC00500000008551203/05/2021SHAILESH OMPRAKASH DASARWAR vs DEVI SHAKTI REALTY LLPorder passed
CC00500000010651802/02/2022Vijay Sadashiv Shinde vs Devi Shakti Realty LLP through its partnersorder passed
CC00500000015727629/06/2022Mallikarjuna S Patil vs Devi Shakti Realty LLPorder passed
CC00500000022836623/02/2023Sunil Vishnupanth Naik vs DEVISHAKTI REALITY LLPorder passed
CC00500000026956016/10/2023Sunil Vishnupanth Naik vs DEVISHAKTI REALITY LLPorder passed
CC00500000025896209/06/2023SUMIT DILIP MALUSARE vs DEVI SHAKTI REALTY LLPorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City CourtRCS431/20072007Suit For Declaration And Injunction
City CourtRCS5909/20122012Suit For Declaration And Injunction Seeking Right To Way Passing Through Out Land

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202330 Dec 2023Dispute between partners, shortage of labour, shortage of Raw Material, inflation as detailed in extension request letter uploaded herewith along with consent from 68% or 2/3 custo

Location, Land & Connectivity

Located at Haveli, Pune, 411060. Per the filed land record, the plot is bounded to the north by S NO 42 PART, to the south by S NO 41 OBLIQUE 1 PART, to the east by S NO 40 PART and to the west by S NO 41 OBLIQUE 5 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT8 km
Pune Junction / city centre11 km
Kharadi / EON IT Park12 km
Pune Int'l Airport (Lohegaon)16 km
Baner–Balewadi belt20 km
Hinjewadi Rajiv Gandhi IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Devi Shakti Realty LLP is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Devi Shakti Realty LLP project & its RERA track record →

Other flagged projects by Devi Shakti Realty LLP

Devi Shakti Realty LLP
Deregistered by MahaRERAPune
Devi Shakti Realty LLP
FlaggedPune

Other RERA-registered projects in Undri

Lodha Pune Nibm Project
possession by Jul 2026 · Lodha Developers Limited
Samarth Rise
possession by Aug 2026 · Shri Samarth Developers
Fortune Prima
possession by Sep 2026 · Satish Shivlal Kokate
Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP

Major developers building in Undri

Other RERA-registered projects in Pune

LA Royale - C Building
declared completion Dec 2022 · Devi Shakti Realty LLP
La Royale - Phase I
declared completion Jan 2021 · Devi Homes
La Ventana Phase 2
declared completion Dec 2022 · Laventana LLP
La Vida
declared completion Jun 2025 · Kakkad Properties
La Vida - Phase 2
declared completion Jun 2025 · Kakkad Properties
LA Villae
possession by Mar 2030 · Taneshq Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026