Lagoona Woods Phase 1

Bhugaon · Sudarshan Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

6units filed as unsoldInventory · 13 September 2026
30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
25registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007392

Delivery and registration

When is the project declared for completion?

Lagoona Woods Phase 1 is registered with MahaRERA as P52100007392 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007392
Registered on17 Aug 2017
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Lagoona Woods Phase 1 record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 35 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sudarshan Developers is the promoter of record on 30 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

30projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Lagoona Woods Phase 1, ₹5.09 Cr of a declared ₹5.14 Cr estimated project cost is reported as incurred, about 98.9%, as at the last certified filing with MahaRERA.

98.9%

₹5.09 Cr

of ₹5.14 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Lagoona Woods Phase 1, 19 of 25 homes filed with MahaRERA are recorded as sold or booked, about 76%, and 6 remain available.

76%sold

19 of 25 homes

₹5.01 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.91 Cr (about 98%) is recorded as collected and ₹10.00 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Ground/Floor 0110,818 sqft (1005 sqm)₹32.66 Lakh
Ground/Floor 0169,386 sqft (872 sqm)₹28.34 Lakh
Ground/Floor 01811,399 sqft (1059 sqm)₹34.42 Lakh
Ground/Floor 02110,602 sqft (985 sqm)₹32.01 Lakh
Ground/Floor 02210,656 sqft (990 sqm)₹32.17 Lakh
Ground/Floor 03511,001 sqft (1022 sqm)₹33.22 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 19 homes carry one, and 6 of the 25 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
110,818 sqftRs 130 a sq ft typical, over Rs 116 to Rs 1693 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Lagoona Woods Phase 1, 2 of the 6 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 5 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1 and 25 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Unit 11G+11-
Unit 21G+11-
Unit 31G+11-
Unit 41G+11-
Unit 51G+11-
Unit 61G+1131 Dec 2018
Unit 71G+11-
Unit 81G+11-
Unit 91G+11-
Unit 101G+11-
Unit 111G+11-
Unit 121G+11-
Unit 131G+1131 May 2019
Unit 141G+11-
Unit 151G+11-
Unit 161G+11-
Unit 171G+1131 Dec 2018
Unit 181G+11-
Unit 191G+11-
Unit 201G+11-
Unit 211G+11-
Unit 221G+11-
Unit 351G+1130 Dec 2020
Unit 361G+11-
Unit 371G+11-

Unit mix on the filing: 25 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020The re validation of the said project was under process. we received the same on 15/12/2018. Because of the market conditions, we couldn't able to sale the whole/ part against the
30 Dec 202031 Dec 2023At the time of registration of the project with MAHARERA, we had planned for the finance form own contribution/ construction finance. However, we could not arrange funds form finan
31 Dec 202330 Jun 2028Reasons for delay. After starting development of site in 2015 it was observed that due to hilly terrain there was plenty of obstruction due to landslides during excavation lack of

Location, Land & Connectivity

Located at Bhugaon, Lavharde, Haveli, Pune, 412115. Per the filed land record, the plot is bounded to the north by 360, to the south by 216, to the east by Lagoona Woods Phase 4 and to the west by Lagoona Woods Phase 2 And 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park13 km
Baner–Balewadi belt15 km
Pune Junction / city centre25 km
Magarpatta / Hadapsar IT30 km
Pune Int'l Airport (Lohegaon)30 km
Kharadi / EON IT Park32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sudarshan Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Bhugaon

Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Asmi Pride
possession by Dec 2026 · M/S Icon Developers
Madhuban
possession by Dec 2026 · NG Rathi Estate
Plumeria, Viva, Pirangut
Deregistered by MahaRERA · possession by Dec 2026 · K Raheja Corp Real Estate Private Limite

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Lake House
declared completion Dec 2021 · Shaila Bhalchandra Gaikwad
Lake Shine
declared completion Jun 2025 · Poorva Developers
Lake Tower
declared completion Apr 2026 · Tushar Pramod Nagarkar
Lake Town D-6, Wing - A And B
declared completion Mar 2026 · Venkatesh Associates
Lake View 6,7,8,9 - Lcl0007
declared completion Dec 2021 · Lavasa Corporation Ltd
Lake Villas
declared completion Dec 2024 · Siddhivinayak Marketing AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026