Plotted Development Intelligence · Pune

KUTUMB BHOOMI

P52100026636 · WADGAON MAVAL · promoter Naiknavare Buildcon Pvt

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100026636
Registered on12 Oct 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Naiknavare Buildcon Pvt is the promoter of record on 34 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division Pune5202013Case Transferred
Bombay High Court12552013Disposed
Sdo Maval5542018Disposed
Sdo Maval Pune2402014Pending
Civil Judge Senior Division Pune1482014Pending

Location, Land & Connectivity

Located at WADGAON MAVAL, HIGHWAY MUMBAI PUNE, Pune City, Pune, 412106. Per the filed land record, the plot is bounded to the north by S NO 126-2 AND BALANCE PORTION OF EAGLES NEST, to the south by S NO 127 PART, to the east by S NO 126-2 and to the west by S NO 122. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Naiknavare Buildcon PVT LTD is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Naiknavare Buildcon PVT LTD project & its RERA track record →

Other flagged projects by Naiknavare Buildcon PVT LTD

Naiknavare Buildcon PVT LTD
FlaggedPune
Naiknavare Buildcon PVT LTD
FlaggedPune
Naiknavare Buildcon PVT LTD
FlaggedPune
Naiknavare Buildcon PVT LTD
FlaggedPune
Naiknavare Buildcon PVT LTD
FlaggedPune
Naiknavare Buildcon PVT LTD
FlaggedPune

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
possession by Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
possession by Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Surya Heights
possession by Dec 2026 · SSB Developer

Major developers building in Vadgaon Maval

Other RERA-registered projects in Pune

Kutumb Bhoomi Phase II
possession by Mar 2027 · Naiknavare Townships LLP & Mr.hemant
Kutumb Prime
declared completion Jun 2023 · Naiknavare Buildcon PVT LTD
Kutumb Prime
declared completion Jun 2023 · Naiknavare Buildcon PVT LTD
Kutumb Prime
declared completion Jun 2024 · Naiknavare Buildcon PVT LTD
Kutumb Prime Project 6
declared completion Jun 2026 · Naiknavare Buildcon Private Limited
L Axis Commercial Centre
possession by Dec 2026 · Pharande Promoters And Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026