31 Dec 2017declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011522

Delivery and registration

When is the project declared for completion?

LODHA BELMONDO ASHBRIDGE D, E is registered with MahaRERA as P52100011522 and the promoter has declared completion for 31 Dec 2017.

31 Dec 2017

declared completion

105months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011522
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 105 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LODHA BELMONDO ASHBRIDGE D, E record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LODHA BELMONDO ASHBRIDGE D, E in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
ASHBRIDGE E1G+2431 Dec 2017
ASHBRIDGE D1G+2431 Dec 2017

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for LODHA BELMONDO ASHBRIDGE D, E, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001114711/03/2018Parag R Kulkarni vs Palava Dwellersorder passed
CC00500000001161809/06/2018VASTIMAL JAIN & OTHER 3 vs PALAVA DWELLERS PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at Ravet, Mumbai City, Mumbai City, 412101. Per the filed land record, the plot is bounded to the north by Gut No 360 Part Only and 226 Part Only, to the south by Gut No 360 Part Only and 226 Part Only, to the east by Gut No 226 Part Only and to the west by Residential. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~55 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park55 km
Baner–Balewadi belt60 km
Pune Junction / city centre71 km
Pune Int'l Airport (Lohegaon)72 km
Kharadi / EON IT Park76 km
Magarpatta / Hadapsar IT76 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 134 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedPune
Lodha Developers Limited
FlaggedPune
Lodha Developers Limited
FlaggedPune
Lodha Developers Limited
FlaggedPune
Lodha Developers Limited
FlaggedPune
Lodha Developers Limited
FlaggedPune

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Lodha Belmondo Augusta C
declared completion Dec 2017 · Lodha Developers Limited
Lodha Belmondo - Estancia B
declared completion Aug 2018 · Lodha Developers Limited
Lodha Belmondo - Pebble Beach D
declared completion Dec 2018 · Lodha Developers Limited
Lodha Belmondo St. Andrews A
possession by Feb 2027 · Lodha Developers Limited
Lodha Belmondo St. Andrews B,c,d Villa 1 To 28
declared completion Jul 2018 · Lodha Developers Limited
Lodha Belmondo ST. Andrews E
declared completion Dec 2019 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026